5810 N SYLVIA AVE 91356

Certificate Information: 5810 N SYLVIA AVE 91356

Application / Permit
24047-20000-00902
Plan Check / Job No.
B24VN09279
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 15' X 26' POOL WITH A 9' X 6' SPA PER STD. PLAN #265
Permit Issued
Issued on 7/5/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2024 APPLICANT
Assigned to Plan Check Engineer 7/1/2024 ISIS ARGUETA
Corrections Issued 7/1/2024 ISIS ARGUETA
Plan Check Approved 7/5/2024 ISIS ARGUETA
Issued 7/5/2024 APPLICANT
CofO in Progress 10/24/2024 MORRIS JACKSON
Permit Finaled 11/4/2024 JOHN JANSON
CofO Issued 11/4/2024 JOHN JANSON
Permit Finaled 11/4/2024 JOHN JANSON

Permit Application Clearance Information

ZA Case Cleared 7/2/2024 STEVEN WECHSLER
ZA Case Cleared 7/2/2024 STEVEN WECHSLER

Contact Information

Contractor G M Gutierrez Construction Company Inc; Lic. No.: 945894-B 15448 ROXFORD STREET      SYLMAR, CA 913421261
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 7/24/2024 Approved ARUTYUN MADATYAN
Pre-Gunite 7/24/2024 Approved ARUTYUN MADATYAN
Rough-Electrical 7/24/2024 Partial Approval ARUTYUN MADATYAN
Rough-Plumbing 7/24/2024 Partial Approval ARUTYUN MADATYAN
Deputy Shotcrete 7/29/2024 Conditional Approval JON MCHUGH
Grounding or Bonding 8/13/2024 Approved MORRIS JACKSON
Enclosure/Fence 9/12/2024 Corrections Issued MORRIS JACKSON
Enclosure/Fence 9/17/2024 Approved MORRIS JACKSON
Final 9/17/2024 Corrections Issued MORRIS JACKSON
Pool Equipment Noise Test 9/30/2024 Approved FELIPE PENICHE
Enclosure/Fence 10/8/2024 Approved MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 10/8/2024 Approved MORRIS JACKSON
Final 10/8/2024 OK to Issue CofO MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Approved MORRIS JACKSON