10025 W SULLY DR 91352
Certificate Information: 10025 W SULLY DR 91352
- Application / Permit
- 24047-20000-00791
- Plan Check / Job No.
- B24VN08141
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Eplan. New pool and spa per engineer design and standard plan 268
- Permit Issued
- Issued on 11/20/2024
- Issuing Office
- Current Status
- CofO Issued on 12/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2024 | KHEDER ALRAZAA |
| Corrections Issued | 7/3/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 7/8/2024 | GARO TELMI |
| Applicant returned to address corrections | 9/25/2024 | KHEDER ALRAZAA |
| Plan Check Approved | 11/14/2024 | KHEDER ALRAZAA |
| Issued | 11/20/2024 | APPLICANT |
| CofO in Progress | 11/12/2025 | DAVID ANDERSON |
| Permit Finaled | 12/12/2025 | RUBEN SALAS |
| CofO Issued | 12/12/2025 | RUBEN SALAS |
| Permit Finaled | 12/12/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/25/2024 | KHEDER ALRAZAA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hagopyan,, Edmond; Lic. No.: C80143 | 3300 FOOTHILL BLVD # 8601 GLENDALE, CA 91214 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Geologist | Carrle,, Conrad Henry; Lic. No.: EG2359 | 23128 WILDWOOD ROAD NEWHALL, CA 91321 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 6/20/2025 | Approved | DAVID ANDERSON |
| Pre-Gunite | 6/20/2025 | Approved | DAVID ANDERSON |
| Grounding or Bonding | 8/12/2025 | Approved | DAVID ANDERSON |
| Enclosure/Fence | 10/22/2025 | Approved | DAVID ANDERSON |
| Pool Equipment Noise Test | 10/29/2025 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 10/31/2025 | Approved | DAVID ANDERSON |
| Final | 10/31/2025 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV Approved | DAVID ANDERSON |