5929 N MELVIN AVE 91356
Certificate Information: 5929 N MELVIN AVE 91356
- Application / Permit
- 24047-20000-00790
- Plan Check / Job No.
- B24VN08124
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan New 12' x 26' pool with a 5' x 12' spa
- Permit Issued
- Issued on 6/17/2024
- Issuing Office
- Current Status
- CofO Issued on 5/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2024 | JOSEPH RAFOLS |
| Corrections Issued | 6/11/2024 | JOSEPH RAFOLS |
| Plan Check Approved | 6/12/2024 | JOSEPH RAFOLS |
| Issued | 6/17/2024 | APPLICANT |
| CofO in Progress | 2/18/2025 | JON MCHUGH |
| Permit Finaled | 5/2/2025 | JOHN JANSON |
| CofO Issued | 5/2/2025 | JOHN JANSON |
| Permit Finaled | 5/2/2025 | JOHN JANSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Agam Pool And Spa Inc; Lic. No.: 993464-C53 | 12940 ADDISON STREET SHERMAN OAKS, CA 91423 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 8/14/2024 | Approved | HENRY KIM |
| Grounding or Bonding | 8/14/2024 | Partial Approval | HENRY KIM |
| Pool Piping | 8/14/2024 | Approved | HENRY KIM |
| Pre-Gunite | 8/14/2024 | Approved | HENRY KIM |
| Rough-Electrical | 8/14/2024 | Approved | HENRY KIM |
| Deputy Shotcrete | 8/19/2024 | Conditional Approval | MORRIS JACKSON |
| Grounding or Bonding | 9/27/2024 | Approved | MORRIS JACKSON |
| Enclosure/Fence | 11/8/2024 | Corrections Issued | MORRIS JACKSON |
| Enclosure/Fence | 1/3/2025 | Approved | JON MCHUGH |
| Final | 1/3/2025 | Corrections Issued | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 1/14/2025 | Approved | JON MCHUGH |
| Final | 1/14/2025 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 1/14/2025 | SGSOV Not Ready | JON MCHUGH |
| Final | 2/14/2025 | Partial Approval | JON MCHUGH |
| Pool Equipment Noise Test | 2/14/2025 | Approved | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 2/14/2025 | SGSOV Approved | JON MCHUGH |
| Final | 2/18/2025 | OK to Issue CofO | JON MCHUGH |