17100 W PARTHENIA ST 91325
Certificate Information: 17100 W PARTHENIA ST 91325
- Application / Permit
- 24047-20000-00747
- Plan Check / Job No.
- B24VN07676
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 32'-0" X 17'-0" POOL WITH ATTACHED 7'-0" X 6'-0" SPA - PER LA CITY STANDARD PLAN 268
- Permit Issued
- Issued on 5/31/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2024 | DANIEL ABRAMYAN |
| Issued | 5/31/2024 | APPLICANT |
| CofO in Progress | 6/24/2025 | NICHOLAS TROWBRIDGE |
| No Progress | 7/28/2025 | RAUL OLAGI |
| CofO in Progress | 7/28/2025 | RAUL OLAGI |
| CofO in Progress | 9/22/2025 | RAUL OLAGI |
| No Progress | 9/22/2025 | RAUL OLAGI |
| CofO in Progress | 9/22/2025 | RAUL OLAGI |
| CofO in Progress | 9/23/2025 | RAUL OLAGI |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
| CofO Issued | 9/24/2025 | RUBEN SALAS |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Valenzuela Pancho Construction; Lic. No.: 1067736-B | 544 ORANGE GROVE AVE SAN FERNANDO, CA 91340 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/25/2024 | Approved | MATTHEW NELSON |
| Rough-Plumbing | 6/25/2024 | Approved | MATTHEW NELSON |
| Deck | 10/18/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Deck | 11/13/2024 | Approved | JAVIER RAMOS JR |
| Enclosure/Fence | 12/23/2024 | Corrections Issued | JAVIER RAMOS JR |
| Final | 6/10/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Pre-Gunite | 6/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 6/10/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Final | 6/23/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Enclosure/Fence | 7/29/2025 | Approved | NICHOLAS TROWBRIDGE |
| Special/Order Compliance | 7/29/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Equipment Noise Level | 9/15/2025 | Approved | FELIPE PENICHE |
| Final | 9/22/2025 | OK to Issue CofO | RAUL OLAGI |