2856 S FORRESTER DR 90064

Certificate Information: 2856 S FORRESTER DR 90064

Application / Permit
24047-20000-00721
Plan Check / Job No.
B24VN07279
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) 12' X 27' POOL WITH 8' X 8' SPA PER STD PLAN #268
Permit Issued
Issued on 5/23/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 ISIS ARGUETA
Plan Check Approved 5/23/2024 ISIS ARGUETA
Issued 5/23/2024 APPLICANT
CofO in Progress 4/24/2025 MICHAEL PELHAM
Permit Finaled 4/24/2025 RICHARD STEINBACH
CofO Issued 4/24/2025 RICHARD STEINBACH
Permit Finaled 4/24/2025 RICHARD STEINBACH

Permit Application Clearance Information

Construction near power lines Cleared 5/23/2024 TINA MIRANDA
Grading Pre-Inspection Cleared 5/23/2024 ISIS ARGUETA

Contact Information

Contractor Plascencia Pools & Landscaping; Lic. No.: 790546-C27 13803 LOUVRE STREET      PACOIMA, CA 91331
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 8/27/2024 No Access for Inspection ASHLEY THOMPSON
Special/Order Compliance 8/27/2024 Partial Inspection REGINA MENDEZ
Excavation/Setback/Form/Re-Bar 8/29/2024 Approved ASHLEY THOMPSON
Pre-Gunite 8/29/2024 Approved ASHLEY THOMPSON
Rough-Electrical 8/29/2024 Approved ASHLEY THOMPSON
Rough-Plumbing 8/29/2024 Partial Approval ASHLEY THOMPSON
Deputy Shotcrete 9/18/2024 Conditional Approval MICHAEL PELHAM
Deck 1/13/2025 Approved JESUS RODRIGUEZ
Enclosure/Fence 3/12/2025 Corrections Issued ASHLEY THOMPSON
Enclosure/Fence 3/14/2025 Approved ARAM AVEDISIAN
Pool Equipment Noise Test 3/20/2025 Approved JUAN ESCOTO DELGADO
Final 3/21/2025 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Not Ready ASHLEY THOMPSON
Final 3/26/2025 Corrections Issued TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 3/26/2025 SGSOV Approved TEMISTOCLES CAAL
Final 4/24/2025 OK to Issue CofO MICHAEL PELHAM