4259 N VANTAGE AVE 91604
Certificate Information: 4259 N VANTAGE AVE 91604
- Application / Permit
- 24047-20000-00690
- Plan Check / Job No.
- B24LA08836
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan New 25' x 14' pool and 7' x 7' 6" spa. All work done per standard details (268) and Engineer details
- Permit Issued
- Issued on 8/8/2024
- Issuing Office
- Current Status
- CofO Issued on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | NAREG ATARIAN |
| Corrections Issued | 5/19/2024 | NAREG ATARIAN |
| Quality Review Completed | 5/21/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/18/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 7/26/2024 | NAREG ATARIAN |
| Plan Check Approved | 7/29/2024 | NAREG ATARIAN |
| Issued | 8/8/2024 | APPLICANT |
| CofO in Progress | 7/23/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
| CofO Issued | 8/5/2025 | RUBEN SALAS |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 6/4/2024 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 12/23/2024 | Conditional Approval | CHRISTOPHE COCHRAN |
| Rough-Electrical | 12/23/2024 | Approved | CHRISTOPHE COCHRAN |
| Deputy Shotcrete | 12/30/2024 | Conditional Approval | ROBERT GOLD |
| Deck | 4/22/2025 | Approved | CHRISTOPHE COCHRAN |
| Enclosure/Fence | 6/5/2025 | Approved | JUAN VALENZUELA |
| Equipment Noise Level | 7/14/2025 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 7/16/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 7/16/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 7/16/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 7/16/2025 | Approved | CHRISTOPHE COCHRAN |
| Pre-Gunite | 7/16/2025 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Not Required | CHRISTOPHE COCHRAN |