727 N LAS PALMAS AVE 90038
Certificate Information: 727 N LAS PALMAS AVE 90038
- Application / Permit
- 24047-20000-00669
- Plan Check / Job No.
- B24VN06771
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL WITH SPA AND BAJA PER STD PLAN #268
- Permit Issued
- Issued on 6/18/2024
- Issuing Office
- Current Status
- CofO Issued on 11/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2024 | ISIS ARGUETA |
| Corrections Issued | 5/15/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 5/28/2024 | ANGELICA DAVE |
| Plan Check Approved | 6/18/2024 | SERGIO MUNIZ |
| Issued | 6/18/2024 | APPLICANT |
| CofO in Progress | 10/10/2024 | BRIAN SULLIVAN |
| Permit Finaled | 11/24/2024 | DEROLD HAUFF |
| CofO Issued | 11/24/2024 | DEROLD HAUFF |
| Permit Finaled | 11/24/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/24/2024 | EDGAR PASCUA |
| Construction within easement | Cleared | 5/24/2024 | EDGAR PASCUA |
Contact Information
| Contractor | G K M Construction; Lic. No.: 444423-B | 17901 PIONEER BLVD #L-363 ARTESIA, CA 90701 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/21/2024 | Approved | JOAQUIN GREENOUGH |
| Gas Piping or Gas Test | 6/21/2024 | Approved | JOAQUIN GREENOUGH |
| Grading Pre-Inspection | 6/21/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Grounding or Bonding | 6/21/2024 | Approved | JOAQUIN GREENOUGH |
| Pool Piping | 6/21/2024 | Approved | JOAQUIN GREENOUGH |
| Pre-Gunite | 6/21/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Rough-Plumbing | 6/21/2024 | Approved | JOAQUIN GREENOUGH |
| Deck | 7/24/2024 | Approved | ROY SPAULDING |
| Enclosure/Fence | 8/1/2024 | Corrections Issued | RAUL BARAJAS |
| Enclosure/Fence | 8/15/2024 | Approved | ROY SPAULDING |
| Final | 8/23/2024 | Corrections Issued | ROY SPAULDING |
| Pre-Gunite | 8/23/2024 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Approved | ROY SPAULDING |
| Pool Equipment Noise Test | 9/3/2024 | Approved | JUAN ESCOTO DELGADO |
| Final | 9/4/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Final | 10/9/2024 | OK to Issue CofO | BRIAN SULLIVAN |