13536 W MORRISON ST 91423
Certificate Information: 13536 W MORRISON ST 91423
- Application / Permit
- 24047-20000-00668
- Plan Check / Job No.
- B24LA08201
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 30' X 15' SWIMMING POOL WITH 9' X 8' ATTACHED SPA AS PER STANDARD PLAN # 268
- Permit Issued
- Issued on 7/2/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | RARES BODEA |
| Corrections Issued | 5/16/2024 | RARES BODEA |
| Quality Review Completed | 5/17/2024 | STEVEN KIM |
| Building Plans Picked Up | 5/17/2024 | APPLICANT |
| Plan Check Approved | 7/2/2024 | RARES BODEA |
| Issued | 7/2/2024 | APPLICANT |
| CofO in Progress | 4/16/2025 | JUAN VALENZUELA |
| CofO Issued | 4/16/2025 | RUBEN SALAS |
| Permit Finaled | 4/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/7/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/7/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| DANIEL ORRANTE, (818) 374-1157 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 8/27/2024 | Corrections Issued | VINCENT HANLEY |
| Pre-Gunite | 8/27/2024 | Corrections Issued | VINCENT HANLEY |
| Deputy Shotcrete | 8/29/2024 | Conditional Approval | JUAN VALENZUELA |
| Rough-Electrical | 12/26/2024 | Approved | JOSE AVILA |
| Rough-Plumbing | 12/26/2024 | Corrections Issued | JOSE AVILA |
| Grounding or Bonding | 1/7/2025 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 2/28/2025 | Corrections Issued | MISAEL ESPARZA |
| Pre-Inspection | 3/19/2025 | Partial Inspection | JUAN VALENZUELA |
| Enclosure/Fence | 3/27/2025 | Approved | JUAN VALENZUELA |
| Pre-Gunite | 3/27/2025 | Conditional Approval | JUAN VALENZUELA |
| Equipment Noise Level | 4/1/2025 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 4/7/2025 | Approved | JUAN VALENZUELA |
| Final | 4/7/2025 | OK to Issue CofO | JUAN VALENZUELA |
| Green Building Final | 4/7/2025 | Approved | JUAN VALENZUELA |
| Green Building Rough | 4/7/2025 | Approved | JUAN VALENZUELA |
| Pre-Gunite | 4/7/2025 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Not Required | JUAN VALENZUELA |