2391 N ACHILLES DR 90046
Certificate Information: 2391 N ACHILLES DR 90046
- Application / Permit
- 24047-20000-00660
- Plan Check / Job No.
- B24VN06646
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL (E) POOL AND SPA TO INSTALL EQUIPMENT, LIGHTING, FILTRATION, AND TO RE-SHAPE INTO A 30'- 5" x 12'-0" SWIMMING POOL WITH ATTCHED 6'-8" x 9'-0" SPA PER CITY STD. PLAN # 268 AND ENGINEERING DETAILS
- Permit Issued
- Issued on 5/13/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2024 | ALFRED RAMIREZ |
| Issued | 5/13/2024 | APPLICANT |
| CofO in Progress | 1/30/2025 | ROY SPAULDING |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
| CofO Issued | 2/9/2025 | DEROLD HAUFF |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/13/2024 | ALFRED RAMIREZ |
Contact Information
| Contractor | Swimming Pool & Spa Surgeon; Lic. No.: 466383-C53 | 4685 RUNWAY STREET UNIT P SIMI VALLEY, CA 93063 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/9/2024 | Conditional Approval | RAUL BARAJAS |
| Pre-Gunite | 7/16/2024 | Approved | RAUL BARAJAS |
| Deputy Shotcrete | 7/18/2024 | Conditional Approval | RAUL BARAJAS |
| Pre-Gunite | 8/12/2024 | Corrections Issued | BRIAN SULLIVAN |
| Grounding or Bonding | 9/24/2024 | Partial Approval | BRIAN SULLIVAN |
| Grounding or Bonding | 10/18/2024 | Approved | BRIAN SULLIVAN |
| Enclosure/Fence | 11/14/2024 | Partial Inspection | BRIAN SULLIVAN |
| Enclosure/Fence | 12/13/2024 | Approved | RAUL BARAJAS |
| Equipment Noise Level | 1/23/2025 | Approved | JUAN ESCOTO DELGADO |
| Final | 1/27/2025 | Corrections Issued | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Approved | ROY SPAULDING |
| Final | 1/29/2025 | OK to Issue CofO | ROY SPAULDING |