638 S WOODRUFF AVE 90024

Certificate Information: 638 S WOODRUFF AVE 90024

Application / Permit
24047-20000-00569
Plan Check / Job No.
B24VN05724
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
BACKFILL PORTION OF (E) POOL (SHELL TO REMAIN) TO REDUCE THE SIZE TO 14'-0" X 30'-0" POOL & 14'-0" X 9'-0" SPA PER STD PLAN # 268 & ENGINEERING DETAILS. ALL WORK DONE WITHIN (E) POOL SHELL.
Permit Issued
Issued on 5/8/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2024 APPLICANT
Assigned to Plan Check Engineer 5/3/2024 ARTIN ZARUKIAN
Corrections Issued 5/4/2024 ARTIN ZARUKIAN
Plan Check Approved 5/6/2024 ARTIN ZARUKIAN
Building Plans Picked Up 5/6/2024 APPLICANT
Issued 5/8/2024 APPLICANT
CofO in Progress 1/13/2025 STEPHANIE SWANSON
CofO Issued 1/15/2025 RICHARD STEINBACH
Permit Finaled 1/15/2025 RICHARD STEINBACH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor J A B S Pools And Spas; Lic. No.: 936142-C53 8055 MATILIJA AVENUE      PANORAMA CITY, CA 91402
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 5/14/2024 Approved STEPHANIE SWANSON
Deck 7/11/2024 Corrections Issued CHRISTOPHER WILSON
Grounding or Bonding 7/11/2024 Not Ready for Inspection CHRISTOPHER WILSON
Deck 7/15/2024 Approved CARLOS MATAMOROS
Grounding or Bonding 7/15/2024 Approved CARLOS MATAMOROS
Special/Order Compliance 7/15/2024 Approved CARLOS MATAMOROS
Enclosure/Fence 9/13/2024 Corrections Issued STEPHANIE SWANSON
Enclosure/Fence 9/23/2024 Corrections Issued STEPHANIE SWANSON
Enclosure/Fence 9/30/2024 Corrections Issued STEPHANIE SWANSON
Enclosure/Fence 10/1/2024 Approved STEPHANIE SWANSON
Equipment Noise Level 10/29/2024 Approved ANDEY CHAPARRO
Pool Equipment Noise Test 10/29/2024 Approved ANDEY CHAPARRO
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Not Ready STEPHANIE SWANSON
Final 1/8/2025 Not Ready for Inspection BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/8/2025 SGSOV Approved BOBBY KEY
Final 1/13/2025 OK to Issue CofO STEPHANIE SWANSON