7455 S MCCONNELL AVE 90045
Certificate Information: 7455 S MCCONNELL AVE 90045
- Application / Permit
- 24047-20000-00470
- Plan Check / Job No.
- B24VN04655
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW (37'-0"x17'-0"), POOL W/(8'-0"x8'-0") SPA ON PILES/GRADE BEAMS PER ENGINEER DESIGN W/POOL COVER
- Permit Issued
- Issued on 1/13/2025
- Issuing Office
- Valley
- Current Status
- Issued on 1/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | PETER MOSESIAN |
| Corrections Issued | 4/25/2024 | PETER MOSESIAN |
| Quality Review Completed | 4/26/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 4/29/2024 | APPLICANT |
| Plan Check Approved | 12/17/2024 | PETER MOSESIAN |
| Issued | 1/13/2025 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 2/24/2025 | Conditional Approval | DAVID FEILER |
| Deputy Other (see comments) | 2/24/2025 | Conditional Approval | HERBERT GIRON |
| Piling/Pier/Caisson | 2/24/2025 | Corrections Issued | HERBERT GIRON |
| Piling/Pier/Caisson | 2/25/2025 | Partial Approval | TEMISTOCLES CAAL |
| Piling/Pier/Caisson | 3/5/2025 | Partial Approval | TEMISTOCLES CAAL |
| Piling/Pier/Caisson | 4/1/2025 | Partial Approval | JESUS PINEDA |
| Deputy Other (see comments) | 4/2/2025 | Conditional Approval | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 4/25/2025 | Partial Approval | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 5/15/2025 | Partial Approval | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 5/20/2025 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 9/18/2025 | Corrections Issued | JESUS PINEDA |
| Grounding or Bonding | 9/22/2025 | Approved | JESUS PINEDA |
| Pre-Gunite | 9/22/2025 | Approved | JESUS PINEDA |
| Rough-Electrical | 9/22/2025 | Partial Approval | JESUS PINEDA |
| Rough-Plumbing | 9/22/2025 | Partial Approval | JESUS PINEDA |
| Deputy Shotcrete | 9/29/2025 | Conditional Approval | JESUS PINEDA |