9100 N PATRICK AVE 91331
Certificate Information: 9100 N PATRICK AVE 91331
- Application / Permit
- 24047-20000-00465
- Plan Check / Job No.
- B24VN04583
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 25'-0" X 20'-0" POOL WITH 6'-0" X 6'-0" SPA PER LA CITY STANDARD PLAN 270
- Permit Issued
- Issued on 7/1/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 4/5/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 6/28/2024 | ISIS ARGUETA |
| Issued | 7/1/2024 | APPLICANT |
| CofO in Progress | 9/5/2024 | VINCENT HANLEY |
| CofO Issued | 9/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/12/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cristescu,, Barbu Dan; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/3/2024 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/11/2024 | Corrections Issued | GREGG CUMMINGS |
| Gas Piping or Gas Test | 7/11/2024 | Approved | GREGG CUMMINGS |
| Grounding or Bonding | 7/11/2024 | Approved | GREGG CUMMINGS |
| Pool Piping | 7/11/2024 | Approved | GREGG CUMMINGS |
| Pre-Gunite | 7/11/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Rough-Plumbing | 7/11/2024 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/16/2024 | Approved | GREGG CUMMINGS |
| Grounding or Bonding | 7/16/2024 | Approved | GREGG CUMMINGS |
| Pool Piping | 7/16/2024 | Approved | GREGG CUMMINGS |
| Rough-Electrical | 7/16/2024 | Approved | GREGG CUMMINGS |
| Rough-Plumbing | 7/16/2024 | Approved | GREGG CUMMINGS |
| Deputy Shotcrete | 7/18/2024 | Conditional Approval | JUAN VALENZUELA |
| Grounding or Bonding | 7/25/2024 | Approved | DAVID ANDERSON |
| Enclosure/Fence | 7/31/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Enclosure/Fence | 8/2/2024 | Approved | JENNIFER RABUCHIN |
| Final | 8/2/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Pre-Gunite | 8/2/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/2/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Pool Equipment Noise Test | 8/22/2024 | Approved | FELIPE PENICHE |
| Final | 8/26/2024 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/26/2024 | SGSOV Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/30/2024 | Approved | VINCENT HANLEY |
| Final | 8/30/2024 | Partial Approval | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Approved | VINCENT HANLEY |
| Final | 9/5/2024 | OK to Issue CofO | VINCENT HANLEY |