4852 N GENTRY AVE 91607

Certificate Information: 4852 N GENTRY AVE 91607

Application / Permit
24047-20000-00419
Plan Check / Job No.
B24VN04145
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 35' x 20' SWIMMING POOL AND 10' x 9' SPA PER STANDARD PLAN #268 AND ENGINEER DETAIL.
Permit Issued
Issued on 4/15/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2024 APPLICANT
Assigned to Plan Check Engineer 4/4/2024 JEROME MAGAT PALMA
Corrections Issued 4/5/2024 JEROME MAGAT PALMA
Applicant returned to address corrections 4/8/2024 MIROOSH KHACHATOORIAN
Building Plans Picked Up 4/8/2024 APPLICANT
Issued 4/15/2024 APPLICANT
CofO in Progress 10/31/2024 CHRISTOPHER ROJAS
CofO Issued 11/1/2024 DANIEL ORRANTE
Permit Finaled 11/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Exclusive Pools Inc; Lic. No.: 343762-B 18017 CHATSWORTH ST      GRANADA HILLS, CA 91344
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 5/31/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Pre-Gunite 5/31/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 6/4/2024 Approved CHRISTOPHER ROJAS
Pre-Gunite 6/4/2024 Approved CHRISTOPHER ROJAS
Deputy Shotcrete 6/11/2024 Conditional Approval JUAN VALENZUELA
Enclosure/Fence 9/18/2024 Conditional Approval CHRISTOPHER ROJAS
Enclosure/Fence 9/26/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Deputy Shotcrete 9/30/2024 Corrections Issued GAREN HAYRAPETYAN
Enclosure/Fence 9/30/2024 Approved GAREN HAYRAPETYAN
Excavation/Setback/Form/Re-Bar 10/16/2024 Partial Inspection CHRISTOPHER ROJAS
Final 10/16/2024 Partial Inspection CHRISTOPHER ROJAS
Green Building Final 10/16/2024 Partial Inspection CHRISTOPHER ROJAS
Pool Equipment Noise Test 10/16/2024 Approved ALFREDO FLORES
SGSOV-Seismic Gas S/O Valve 10/16/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 10/29/2024 Approved CHRISTOPHER ROJAS
Final 10/29/2024 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 10/29/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Approved CHRISTOPHER ROJAS