4979 E CORINGA DR 90042
Certificate Information: 4979 E CORINGA DR 90042
- Application / Permit
- 24047-20000-00416
- Plan Check / Job No.
- B24VN04130
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New 16' x 28' pool and 16' x 9' 4" spa. All work done per engineer.
- Permit Issued
- Issued on 9/17/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | NAREG ATARIAN |
| Corrections Issued | 4/6/2024 | NAREG ATARIAN |
| Quality Review Completed | 4/8/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 4/10/2024 | APPLICANT |
| Applicant returned to address corrections | 8/14/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 9/4/2024 | NAREG ATARIAN |
| Plan Check Approved | 9/13/2024 | NAREG ATARIAN |
| Issued | 9/17/2024 | APPLICANT |
| CofO in Progress | 2/27/2025 | BRENDAN MORELLI |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
| CofO Issued | 3/2/2025 | DEROLD HAUFF |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/14/2024 | ROBERT HUGHES |
Contact Information
| Architect | , ; Lic. No.: C39885 | 4000 SAN RAFAEL AVE LOS ANGELES, CA 90065 |
| Contractor | Aqua Pool & Spa Construction Inc; Lic. No.: 1046115-C53 | 7361 ETHEL AVE #4 NORTH HOLLYWOOD, CA 91605 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
| Engineer | Guzman,, Martin; Lic. No.: C79193 | 4358 SEPULVEDA BLVD CULVER CITY, CA 90230 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 10/10/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 10/10/2024 | Approved | ROY SPAULDING |
| Pre-Gunite | 10/10/2024 | Approved | ROY SPAULDING |
| Pre-Inspection | 10/11/2024 | Approved | ROY SPAULDING |
| Deputy Shotcrete | 10/15/2024 | Conditional Approval | ROY SPAULDING |
| Deck | 12/12/2024 | Not Ready for Inspection | ROY SPAULDING |
| Deck | 12/24/2024 | Approved | BRENDAN MORELLI |
| Enclosure/Fence | 12/24/2024 | Approved | BRENDAN MORELLI |
| Pool Equipment Noise Test | 2/25/2025 | Approved | ANDEY CHAPARRO |
| Excavation/Setback/Form/Re-Bar | 2/26/2025 | Approved | BRENDAN MORELLI |
| Final | 2/26/2025 | OK to Issue CofO | BRENDAN MORELLI |
| Green Building Final | 2/26/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Approved | BRENDAN MORELLI |