3105 N ELVIDO DR 90049
Certificate Information: 3105 N ELVIDO DR 90049
- Application / Permit
- 24047-20000-00370
- Plan Check / Job No.
- B24VN03589
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW 30'X16' SWIMMING POOL W/ 8'-0"X 8'-0" SPA PER CITY STD PLAN #268 W/ SUPPL ENGR DETAILS.
- Permit Issued
- Issued on 4/12/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 3/27/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 3/29/2024 | APPLICANT |
| Plan Check Approved | 4/11/2024 | GIOVANNY CHAVEZ |
| Issued | 4/12/2024 | APPLICANT |
| CofO in Progress | 10/10/2024 | KEVIN SARGSYAN |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
| CofO Issued | 10/15/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/28/2024 | ALEX VELA |
| Specific Plan | Cleared | 3/28/2024 | ALEX VELA |
| Specific Plan | Cleared | 3/28/2024 | ALEX VELA |
Contact Information
| Contractor | M A Custom Pools Inc; Lic. No.: 1067000-C53 | 29405 LUZON DR SANTA CLARITA, CA 91390 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/3/2024 | Approved | KEVIN SARGSYAN |
| Deputy Shotcrete | 5/6/2024 | Conditional Approval | KEVIN SARGSYAN |
| Grounding or Bonding | 5/17/2024 | Approved | KEVIN SARGSYAN |
| Enclosure/Fence | 8/13/2024 | Corrections Issued | KEVIN SARGSYAN |
| Enclosure/Fence | 8/29/2024 | Approved | KEVIN SARGSYAN |
| Pool Equipment Noise Test | 9/10/2024 | Approved | EUSEBIO GUZMAN |
| Final | 10/7/2024 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Gunite | 10/7/2024 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/7/2024 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 10/9/2024 | OK to Issue CofO | KEVIN SARGSYAN |