3307 N BLAIR DR 90068

Certificate Information: 3307 N BLAIR DR 90068

Application / Permit
24047-20000-00367
Plan Check / Job No.
B24VN03521
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New (26'-1" x 20'-6" Irregular Shape) Swimming Pool with Interior Spa on Grade Beams and Piles per Engineering.
Permit Issued
Issued on 11/13/2024
Issuing Office
Current Status
Issued on 11/13/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/15/2024 APPLICANT
Assigned to Plan Check Engineer 3/21/2024 VAHAN JIVALAGIAN
Corrections Issued 3/24/2024 VAHAN JIVALAGIAN
Quality Review Completed 3/27/2024 OMID HEDAYAT
Building Plans Picked Up 4/10/2024 APPLICANT
Applicant returned to address corrections 4/30/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 10/9/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 10/31/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 11/4/2024 VAHAN JIVALAGIAN
Plan Check Approved 11/13/2024 VAHAN JIVALAGIAN
Issued 11/13/2024 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/9/2024 VAHAN JIVALAGIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 1543      HAWTHORNE, CA 90251
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Geologist Hill,, Thomas George; Lic. No.: EG1100 3210 VAL VERDE      LONG BEACH, CA 90808

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 5/7/2025 Corrections Issued BRIAN SULLIVAN
Piling/Pier/Caisson 5/9/2025 Not Ready for Inspection BRIAN SULLIVAN
Deputy Other (see comments) 6/5/2025 Approved BRIAN SULLIVAN
Piling/Pier/Caisson 6/5/2025 Approved BRIAN SULLIVAN
Deputy Other (see comments) 6/12/2025 Conditional Approval JOSH MEISTER
Deputy Other (see comments) 6/13/2025 Conditional Approval JOSH MEISTER
Deputy Drilled-In Anchors 9/10/2025 Conditional Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 9/11/2025 Partial Approval BRIAN SULLIVAN
Deputy Other (see comments) 9/12/2025 Conditional Approval ROY SPAULDING
Rough-Plumbing 2/2/2026 Corrections Issued ROY SPAULDING
Special/Order Compliance 2/2/2026 Partial Inspection BRIAN SULLIVAN
Rough-Plumbing 2/5/2026 Approved ROY SPAULDING
Green Building Rough 2/9/2026 Approved ROY SPAULDING
Pre-Gunite 2/9/2026 Approved ROY SPAULDING
Special/Order Compliance 2/9/2026 Partial Inspection BRIAN SULLIVAN
Special/Order Compliance 3/11/2026 Partial Inspection BRIAN SULLIVAN