12317 W HATTERAS ST 91607
Certificate Information: 12317 W HATTERAS ST 91607
- Application / Permit
- 24047-20000-00363
- Plan Check / Job No.
- B24VN03511
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 14'-0" X 25'-10" POOL w/ 8' X 8' SPA AND BAJA PER LA STANDARD PLAN# 268 AND ENGINEERED DETAILS
- Permit Issued
- Issued on 6/7/2024
- Issuing Office
- Current Status
- CofO Issued on 3/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2024 | JESSE ARELLANO |
| Corrections Issued | 3/28/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 4/22/2024 | APPLICANT |
| Plan Check Approved | 6/7/2024 | ISIS ARGUETA |
| Issued | 6/7/2024 | APPLICANT |
| CofO in Progress | 2/27/2025 | RAUL OLAGI |
| Permit Finaled | 3/3/2025 | RUBEN SALAS |
| CofO Issued | 3/3/2025 | RUBEN SALAS |
| Permit Finaled | 3/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/10/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/10/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 7/18/2024 | Approved | OGANES TARAKHCHYAN |
| Rough-Electrical | 7/18/2024 | Approved | OGANES TARAKHCHYAN |
| Rough-Plumbing | 7/18/2024 | Approved | OGANES TARAKHCHYAN |
| Deputy Shotcrete | 7/22/2024 | Conditional Approval | JUAN VALENZUELA |
| Gas Piping or Gas Test | 10/21/2024 | Approved | GAREN HAYRAPETYAN |
| Deck | 11/7/2024 | Approved | OGANES TARAKHCHYAN |
| Enclosure/Fence | 12/27/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Enclosure/Fence | 12/30/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Enclosure/Fence | 12/31/2024 | Approved | OGANES TARAKHCHYAN |
| Pool Equipment Noise Test | 1/15/2025 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 1/16/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 1/16/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 1/16/2025 | SGSOV Approved | OGANES TARAKHCHYAN |