19142 W KESWICK ST 91335

Certificate Information: 19142 W KESWICK ST 91335

Application / Permit
24047-20000-00326
Plan Check / Job No.
B24VN03243
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 20'-0" X 12'-0" POOL WITH 7'-0" X 6'-0" SPA - PER LA CITY STANDARD PLAN
Permit Issued
Issued on 6/18/2024
Issuing Office
Current Status
CofO Issued on 4/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2024 APPLICANT
Assigned to Plan Check Engineer 3/14/2024 DANIEL ABRAMYAN
Corrections Issued 3/14/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 3/26/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 4/22/2024 DANIEL ABRAMYAN
Plan Check Approved 6/13/2024 DANIEL ABRAMYAN
Issued 6/18/2024 APPLICANT
CofO in Progress 3/19/2025 ARUTYUN MADATYAN
Permit Finaled 4/7/2025 JOHN JANSON
CofO Issued 4/7/2025 JOHN JANSON
Permit Finaled 4/7/2025 JOHN JANSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Susan Development And Construction Inc; Lic. No.: 1089492-B       ,
Engineer Cristescu,, Barbu Dan; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 6/28/2024 Corrections Issued SEAN WIRCH
Gas Piping or Gas Test 8/1/2024 Approved JEFFREY BULL
Pre-Gunite 8/1/2024 Approved JEFFREY BULL
Rough-Electrical 8/1/2024 Approved JEFFREY BULL
Rough-Plumbing 8/1/2024 Approved JEFFREY BULL
Deputy Shotcrete 8/5/2024 Partial Approval SEAN WIRCH
Grounding or Bonding 9/19/2024 Approved JEFFREY BULL
Enclosure/Fence 2/24/2025 Approved ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 2/24/2025 Approved ARUTYUN MADATYAN
Final 2/24/2025 Not Ready for Inspection ARUTYUN MADATYAN
Pool Equipment Noise Test 2/24/2025 Approved FELIPE PENICHE
SGSOV-Seismic Gas S/O Valve 2/24/2025 SGSOV Approved ARUTYUN MADATYAN
ELECTRICAL-Final 3/18/2025 Approved ARUTYUN MADATYAN
Final 3/18/2025 OK to Issue CofO ARUTYUN MADATYAN