20211 W LIVERPOOL WAY 91326
Certificate Information: 20211 W LIVERPOOL WAY 91326
- Application / Permit
- 24047-20000-00313
- Plan Check / Job No.
- B24VN03125
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 21' X 29' POOL WITH 9' X 9' SPA PER STD PLAN #268 AND ENGINEERED DETAILS
- Permit Issued
- Issued on 6/28/2024
- Issuing Office
- Current Status
- CofO Issued on 10/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2024 | ISIS ARGUETA |
| Corrections Issued | 3/13/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 4/10/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 4/30/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 5/3/2024 | ISIS ARGUETA |
| Plan Check Approved | 6/27/2024 | ISIS ARGUETA |
| Issued | 6/28/2024 | APPLICANT |
| CofO in Progress | 10/11/2024 | JEFFREY PARD |
| Permit Finaled | 10/22/2024 | JOHN JANSON |
| CofO Issued | 10/22/2024 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/10/2024 | ISIS ARGUETA |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2024 | EDGAR ALCARAZ |
| Watercourse | Cleared | 5/3/2024 | EDGAR ALCARAZ |
| "T" removal | Cleared | 5/8/2024 | ASHLEY RODARTE |
| CPC | Cleared | 5/8/2024 | ASHLEY RODARTE |
| CPC | Cleared | 5/8/2024 | ASHLEY RODARTE |
| CPC | Cleared | 5/8/2024 | ASHLEY RODARTE |
| ZA Case | Cleared | 5/8/2024 | ASHLEY RODARTE |
| ZA Case | Cleared | 5/8/2024 | ASHLEY RODARTE |
| Construction near power lines | Cleared | 6/21/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/22/2024 | Corrections Issued | JEFFREY PARD |
| Pre-Gunite | 7/22/2024 | Corrections Issued | JEFFREY PARD |
| Rough-Electrical | 7/22/2024 | Approved | JEFFREY PARD |
| Rough-Plumbing | 7/22/2024 | Approved | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 7/29/2024 | Approved | JEFFREY PARD |
| Gas Piping or Gas Test | 7/29/2024 | Approved | JEFFREY PARD |
| Grounding or Bonding | 7/29/2024 | Partial Approval | JEFFREY PARD |
| Pool Piping | 7/29/2024 | Approved | JEFFREY PARD |
| Pre-Gunite | 7/29/2024 | Approved | JEFFREY PARD |
| Rough-Electrical | 7/29/2024 | Approved | JEFFREY PARD |
| Rough-Plumbing | 7/29/2024 | Approved | JEFFREY PARD |
| Deck | 9/18/2024 | Approved | JEFFREY PARD |
| Enclosure/Fence | 9/18/2024 | Corrections Issued | JEFFREY PARD |
| Grounding or Bonding | 9/18/2024 | Approved | JEFFREY PARD |
| Pool/Spa Cover | 9/18/2024 | Not Ready for Inspection | JEFFREY PARD |
| Enclosure/Fence | 10/1/2024 | Approved | JEFFREY PARD |
| Pool/Spa Cover | 10/1/2024 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Final | 10/8/2024 | Approved | JEFFREY PARD |
| Final | 10/8/2024 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Final | 10/8/2024 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 10/8/2024 | SGSOV Approved | JEFFREY PARD |
| Equipment Noise Level | 10/9/2024 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 10/10/2024 | Approved | JEFFREY PARD |
| Final | 10/10/2024 | OK to Issue CofO | JEFFREY PARD |
| PLUMBING-Final | 10/10/2024 | Approved | JEFFREY PARD |