20211 W LIVERPOOL WAY 91326

Certificate Information: 20211 W LIVERPOOL WAY 91326

Application / Permit
24047-20000-00313
Plan Check / Job No.
B24VN03125
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) 21' X 29' POOL WITH 9' X 9' SPA PER STD PLAN #268 AND ENGINEERED DETAILS
Permit Issued
Issued on 6/28/2024
Issuing Office
Current Status
CofO Issued on 10/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2024 APPLICANT
Assigned to Plan Check Engineer 3/12/2024 ISIS ARGUETA
Corrections Issued 3/13/2024 ISIS ARGUETA
Applicant returned to address corrections 4/10/2024 ISIS ARGUETA
Applicant returned to address corrections 4/30/2024 ISIS ARGUETA
Applicant returned to address corrections 5/3/2024 ISIS ARGUETA
Plan Check Approved 6/27/2024 ISIS ARGUETA
Issued 6/28/2024 APPLICANT
CofO in Progress 10/11/2024 JEFFREY PARD
Permit Finaled 10/22/2024 JOHN JANSON
CofO Issued 10/22/2024 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/10/2024 ISIS ARGUETA
Eng Process Fee Ord 176,300 Cleared 5/2/2024 EDGAR ALCARAZ
Watercourse Cleared 5/3/2024 EDGAR ALCARAZ
"T" removal Cleared 5/8/2024 ASHLEY RODARTE
CPC Cleared 5/8/2024 ASHLEY RODARTE
CPC Cleared 5/8/2024 ASHLEY RODARTE
CPC Cleared 5/8/2024 ASHLEY RODARTE
ZA Case Cleared 5/8/2024 ASHLEY RODARTE
ZA Case Cleared 5/8/2024 ASHLEY RODARTE
Construction near power lines Cleared 6/21/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/22/2024 Corrections Issued JEFFREY PARD
Pre-Gunite 7/22/2024 Corrections Issued JEFFREY PARD
Rough-Electrical 7/22/2024 Approved JEFFREY PARD
Rough-Plumbing 7/22/2024 Approved JEFFREY PARD
Excavation/Setback/Form/Re-Bar 7/29/2024 Approved JEFFREY PARD
Gas Piping or Gas Test 7/29/2024 Approved JEFFREY PARD
Grounding or Bonding 7/29/2024 Partial Approval JEFFREY PARD
Pool Piping 7/29/2024 Approved JEFFREY PARD
Pre-Gunite 7/29/2024 Approved JEFFREY PARD
Rough-Electrical 7/29/2024 Approved JEFFREY PARD
Rough-Plumbing 7/29/2024 Approved JEFFREY PARD
Deck 9/18/2024 Approved JEFFREY PARD
Enclosure/Fence 9/18/2024 Corrections Issued JEFFREY PARD
Grounding or Bonding 9/18/2024 Approved JEFFREY PARD
Pool/Spa Cover 9/18/2024 Not Ready for Inspection JEFFREY PARD
Enclosure/Fence 10/1/2024 Approved JEFFREY PARD
Pool/Spa Cover 10/1/2024 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Final 10/8/2024 Approved JEFFREY PARD
Final 10/8/2024 Corrections Issued JEFFREY PARD
PLUMBING-Final 10/8/2024 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Approved JEFFREY PARD
Equipment Noise Level 10/9/2024 Approved FELIPE PENICHE
ELECTRICAL-Final 10/10/2024 Approved JEFFREY PARD
Final 10/10/2024 OK to Issue CofO JEFFREY PARD
PLUMBING-Final 10/10/2024 Approved JEFFREY PARD