6652 E HOUGH ST 90042
Certificate Information: 6652 E HOUGH ST 90042
- Application / Permit
- 24047-20000-00288
- Plan Check / Job No.
- B24VN02841
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15'-8" X 25'-0" POOL PER LA CITY STD PLAN No. 268
- Permit Issued
- Issued on 4/17/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 3/4/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/17/2024 | KHUONG TRUONG |
| Issued | 4/17/2024 | APPLICANT |
| CofO in Progress | 4/27/2026 | DAVID WILLIAMS |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
| CofO Issued | 4/30/2026 | DEROLD HAUFF |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/17/2024 | KHUONG TRUONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/21/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Grading Pre-Inspection | 5/21/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Pool Piping | 5/21/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Pre-Gunite | 5/21/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 5/30/2024 | Approved | ALIZAH MAYAGOITIA |
| Pool Piping | 5/30/2024 | Approved | ALIZAH MAYAGOITIA |
| Pre-Gunite | 5/30/2024 | Approved | ALIZAH MAYAGOITIA |
| Pre-Inspection | 5/30/2024 | Approved | ALIZAH MAYAGOITIA |
| Deputy Shotcrete | 6/10/2024 | Conditional Approval | CRAIG VAUGHAN |
| Deck | 10/10/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Enclosure/Fence | 10/10/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Deck | 10/18/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Enclosure/Fence | 10/18/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deck | 11/21/2024 | Approved | ALIZAH MAYAGOITIA |
| Enclosure/Fence | 11/21/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Grounding or Bonding | 11/21/2024 | Approved | ALIZAH MAYAGOITIA |
| Enclosure/Fence | 2/7/2025 | Corrections Issued | CRAIG DAVIS |
| Enclosure/Fence | 2/12/2025 | Approved | CRAIG DAVIS |
| Final | 3/4/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 3/4/2026 | SGSOV Approved | DAVID WILLIAMS |
| Final | 3/24/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Grading Pre-Inspection | 3/26/2026 | Approved | RONNIE MEDINA |
| Final | 4/27/2026 | OK to Issue CofO | DAVID WILLIAMS |