8310 N FAUST AVE 91304

Certificate Information: 8310 N FAUST AVE 91304

Application / Permit
24047-20000-00259
Plan Check / Job No.
B24VN02574
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 34' X 14" POOL WITH 7' X 8' SPA PER STANDARD PLAN 268
Permit Issued
Issued on 2/27/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2024 APPLICANT
Assigned to Plan Check Engineer 2/27/2024 ALEC MOUSAKHANIAN
Plan Check Approved 2/27/2024 ALEC MOUSAKHANIAN
Issued 2/27/2024 APPLICANT
CofO in Progress 9/12/2024 CHRIS CHRISTENSEN
CofO Issued 9/30/2024 JOHN JANSON
Permit Finaled 9/30/2024 JOHN JANSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Barajas Pool And Spa Plumbing Concrete And Repair Inc; Lic. No.: 1007202-C53 45124 93RD ST WEST      LANCASTER, CA 93536

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 3/20/2024 Approved CHRIS CHRISTENSEN
Deputy Shotcrete 3/21/2024 Conditional Approval CHRIS CHRISTENSEN
Deck 4/17/2024 Approved CHRIS CHRISTENSEN
Enclosure/Fence 5/16/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Enclosure/Fence 5/20/2024 No Access for Inspection CHRIS CHRISTENSEN
Enclosure/Fence 5/28/2024 Corrections Issued CHRIS CHRISTENSEN
Enclosure/Fence 5/30/2024 Approved CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 7/5/2024 Not Ready for Inspection JEFFREY HARTLINE
Final 7/5/2024 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 7/5/2024 SGSOV Not Ready JEFFREY HARTLINE
Pool Equipment Noise Test 7/9/2024 No Access for Inspection ALFREDO FLORES
Pool Equipment Noise Test 7/11/2024 Approved ALFREDO FLORES
Excavation/Setback/Form/Re-Bar 7/29/2024 No Access for Inspection JEFFREY HARTLINE
Final 7/29/2024 No Access for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Not Ready JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 8/7/2024 SGSOV Not Ready JEFFREY HARTLINE
Excavation/Setback/Form/Re-Bar 8/22/2024 Approved JEFFREY HARTLINE
Final 8/22/2024 Corrections Issued JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 8/22/2024 SGSOV Approved JEFFREY HARTLINE
Final 9/6/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Final 9/11/2024 OK to Issue CofO CHRIS CHRISTENSEN