10323 W VALLEY SPRING LANE 91602
Certificate Information: 10323 W VALLEY SPRING LANE 91602
- Application / Permit
- 24047-20000-00217
- Plan Check / Job No.
- B24VN02091
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW 33'X9' SWIMMING POOL W/ SPA PER CITY STD PLAN #268 & SUPPLEMENTAL ENGR DETAILS. SEE COMMENTS.
- Permit Issued
- Issued on 8/1/2024
- Issuing Office
- Current Status
- CofO Issued on 4/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 2/16/2024 | HAYATO TSUCHIYA |
| Plan Check Approved | 8/1/2024 | HAYATO TSUCHIYA |
| Issued | 8/1/2024 | APPLICANT |
| CofO in Progress | 4/29/2025 | JUAN VALENZUELA |
| Permit Finaled | 4/29/2025 | RUBEN SALAS |
| CofO Issued | 4/29/2025 | RUBEN SALAS |
| Permit Finaled | 4/29/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/26/2024 | ENRIQUE ACOSTA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 8/23/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pool Equipment Noise Test | 8/23/2024 | Not Ready for Inspection | FELIPE PENICHE |
| Pool Piping | 8/23/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pre-Gunite | 8/23/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Rough-Electrical | 8/23/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Rough-Plumbing | 8/23/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 9/13/2024 | Approved | CHRISTOPHER ROJAS |
| Gas Piping or Gas Test | 9/13/2024 | Approved | CHRISTOPHER ROJAS |
| Pool Piping | 9/13/2024 | Approved | CHRISTOPHER ROJAS |
| Rough-Electrical | 9/13/2024 | Approved | CHRISTOPHER ROJAS |
| Rough-Plumbing | 9/13/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 10/31/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Enclosure/Fence | 11/5/2024 | Approved | CHRISTOPHER ROJAS |
| Pool Equipment Noise Test | 4/1/2025 | Approved | FELIPE PENICHE |
| Final | 4/2/2025 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Gunite | 4/2/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Not Required | JAVIER RAMOS JR |
| Final | 4/28/2025 | OK to Issue CofO | JUAN VALENZUELA |