20133 W GAULT ST 91306
Certificate Information: 20133 W GAULT ST 91306
- Application / Permit
- 24047-20000-00212
- Plan Check / Job No.
- B24VN02008
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16'-0" X 11'-0" SPA PER LA CITY STANDARD PLAN #265 AND SUPPLEMENTAL ENGINEERED DETAIL
- Permit Issued
- Issued on 1/8/2025
- Issuing Office
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 2/23/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 4/16/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 7/16/2024 | ISIS ARGUETA |
| Plan Check Approved | 10/20/2024 | DANIEL ABRAMYAN |
| Issued | 1/8/2025 | APPLICANT |
| CofO in Progress | 5/27/2025 | ALEXANDER HANDY |
| Permit Finaled | 6/3/2025 | JOHN JANSON |
| CofO Issued | 6/3/2025 | JOHN JANSON |
| Permit Finaled | 6/3/2025 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/20/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/15/2025 | Approved | ALEXANDER HANDY |
| Rough-Electrical | 1/15/2025 | Approved | ALEXANDER HANDY |
| Rough-Plumbing | 1/15/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 4/8/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Enclosure/Fence | 4/8/2025 | Approved | JUAN ALVARADO |
| Equipment Noise Level | 4/8/2025 | Not Ready for Inspection | FELIPE PENICHE |
| PLUMBING-Final | 4/8/2025 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Final | 4/29/2025 | Corrections Issued | JUAN ALVARADO |
| Final | 4/29/2025 | Not Ready for Inspection | JUAN ALVARADO |
| PLUMBING-Final | 4/29/2025 | Approved | JUAN ALVARADO |
| Pool Equipment Noise Test | 4/29/2025 | Approved | ALFREDO FLORES |
| Pre-Gunite | 4/29/2025 | Approved | JUAN ALVARADO |
| Final | 5/20/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Deputy Shotcrete | 5/27/2025 | Conditional Approval | ALEXANDER HANDY |
| Final | 5/27/2025 | OK to Issue CofO | ALEXANDER HANDY |