5300 N DUBOIS AVE 91367
Certificate Information: 5300 N DUBOIS AVE 91367
- Application / Permit
- 24047-20000-00149
- Plan Check / Job No.
- B24VN01321
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 30'-0" X 14'-0" POOL WITH A 8'-0" X 8'-0" SPA PER LA CITY STD PLAN No. 268
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Current Status
- CofO Issued on 9/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 1/31/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/22/2024 | OMAR GARNICA |
| Issued | 4/22/2024 | APPLICANT |
| CofO in Progress | 8/15/2024 | TROY SANDERS |
| CofO Issued | 9/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/31/2024 | LUISANGEL VALENZUELA |
| Construction near power lines | Cleared | 4/18/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Intex Design And Construction Inc; Lic. No.: 981718-B | 15021 VENTURA BLVD STE 520 SHERMAN OAKS, CA 91403 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/30/2024 | Approved | TROY SANDERS |
| Rough-Electrical | 5/30/2024 | Approved | TROY SANDERS |
| Rough-Plumbing | 5/30/2024 | Approved | TROY SANDERS |
| Deputy Shotcrete | 6/5/2024 | Conditional Approval | GEVORK IPCHYAN |
| Deck | 7/11/2024 | Approved | TROY SANDERS |
| Grounding or Bonding | 7/11/2024 | Approved | TROY SANDERS |
| Enclosure/Fence | 7/18/2024 | Not Ready for Inspection | TROY SANDERS |
| Enclosure/Fence | 7/23/2024 | Approved | TROY SANDERS |
| Equipment Noise Level | 8/9/2024 | Approved | ALFREDO FLORES |
| Pool Equipment Noise Test | 8/9/2024 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 8/12/2024 | Approved | TROY SANDERS |
| Final | 8/12/2024 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/12/2024 | SGSOV Approved | TROY SANDERS |
| Final | 8/15/2024 | OK to Issue CofO | TROY SANDERS |