13524 W LULL ST 91402
Certificate Information: 13524 W LULL ST 91402
- Application / Permit
- 24047-20000-00129
- Plan Check / Job No.
- B24VN01116
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL (E) POOL PER STD PLAN #268 AND ENGR DETAIL #640 - WORK WITHIN EXISTING POOL SHELL
- Permit Issued
- Issued on 1/26/2024
- Issuing Office
- Current Status
- CofO Issued on 8/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2024 | ISIS ARGUETA |
| Plan Check Approved | 1/26/2024 | ISIS ARGUETA |
| Issued | 1/26/2024 | APPLICANT |
| CofO in Progress | 7/30/2024 | VINCENT HANLEY |
| CofO Issued | 8/6/2024 | RUBEN SALAS |
| Permit Finaled | 8/6/2024 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/31/2024 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 2/8/2024 | Approved | CHRISTOPHER ROJAS |
| Grounding or Bonding | 2/8/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 2/8/2024 | Approved | CHRISTOPHER ROJAS |
| Pool Piping | 2/16/2024 | Corrections Issued | ROBERT GOLD |
| Rough-Electrical | 2/16/2024 | Not Ready for Inspection | ROBERT GOLD |
| Rough-Plumbing | 2/16/2024 | Approved | ROBERT GOLD |
| Gas Piping or Gas Test | 2/22/2024 | Corrections Issued | GREGG CUMMINGS |
| Rough-Electrical | 2/22/2024 | Partial Approval | GREGG CUMMINGS |
| Rough-Plumbing | 2/22/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Gas Piping or Gas Test | 2/29/2024 | Approved | GREGG CUMMINGS |
| Rough-Plumbing | 2/29/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/29/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Grounding or Bonding | 4/12/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Deck | 5/1/2024 | Approved | GREGG CUMMINGS |
| Grounding or Bonding | 5/1/2024 | Approved | GREGG CUMMINGS |
| Pre-Inspection | 5/1/2024 | Approved | GREGG CUMMINGS |
| Enclosure/Fence | 5/21/2024 | Corrections Issued | GREGG CUMMINGS |
| Enclosure/Fence | 5/23/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/28/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Enclosure/Fence | 5/28/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 5/28/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Enclosure/Fence | 5/29/2024 | Approved | VINCENT HANLEY |
| Final | 6/5/2024 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Approved | GREGG CUMMINGS |
| Pool Equipment Noise Test | 6/20/2024 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 7/29/2024 | Approved | VINCENT HANLEY |
| Final | 7/29/2024 | OK to Issue CofO | VINCENT HANLEY |