11612 W LA MAIDA ST 91601
Certificate Information: 11612 W LA MAIDA ST 91601
- Application / Permit
- 24047-20000-00120
- Plan Check / Job No.
- B24VN01003
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- 32'-0" X 17'-0" NEW POOL WITH 7'-0" X 7'-0" SPA PER LA CITY STANDARD PLAN 268 AND SUPPLEMENTAL ENGINEERED DETAIL
- Permit Issued
- Issued on 2/23/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 1/25/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 1/25/2024 | DANIEL ABRAMYAN |
| Issued | 2/23/2024 | APPLICANT |
| CofO in Progress | 11/12/2024 | RAUL OLAGI |
| Permit Finaled | 11/12/2024 | DANIEL ORRANTE |
| CofO Issued | 11/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gunite | 3/28/2024 | Partial Inspection | MISAEL ESPARZA |
| Pre-Gunite | 3/29/2024 | Corrections Issued | JUAN VALENZUELA |
| Gunite | 4/3/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Special/Order Compliance | 4/3/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Gunite | 4/4/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Pre-Gunite | 4/4/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Special/Order Compliance | 4/4/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Pre-Gunite | 6/26/2024 | Approved | CHRISTOPHER ROJAS |
| Rough-Electrical | 8/22/2024 | Approved | CHRISTOPHER ROJAS |
| Rough-Plumbing | 8/22/2024 | Approved | CHRISTOPHER ROJAS |
| Enclosure/Fence | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 10/8/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 10/8/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/8/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Equipment Noise Level | 10/11/2024 | Approved | FELIPE PENICHE |
| Final | 10/11/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Pool Equipment Noise Test | 10/11/2024 | Approved | FELIPE PENICHE |
| Equipment Noise Level | 10/16/2024 | Approved | ALFREDO FLORES |
| Pool Equipment Noise Test | 10/16/2024 | Approved | ALFREDO FLORES |
| Final | 10/17/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Shotcrete | 10/25/2024 | Conditional Approval | RAUL OLAGI |
| Final | 10/25/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 11/12/2024 | OK to Issue CofO | RAUL OLAGI |