11559 W LA MAIDA ST 91601
Certificate Information: 11559 W LA MAIDA ST 91601
- Application / Permit
- 24047-20000-00116
- Plan Check / Job No.
- B24VN00989
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- **ePlan** (E) Swimming pool alteration to reduce size of pool, all work per Standard Plan #265 --1 of 2--
- Permit Issued
- Issued on 2/13/2024
- Issuing Office
- Current Status
- CofO Issued on 10/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2024 | EDWIN ESPIN |
| Corrections Issued | 2/5/2024 | EDWIN ESPIN |
| Plan Check Approved | 2/12/2024 | EDWIN ESPIN |
| Issued | 2/13/2024 | APPLICANT |
| CofO in Progress | 10/7/2025 | MISAEL ESPARZA |
| CofO Issued | 10/28/2025 | RUBEN SALAS |
| Permit Finaled | 10/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 2/8/2024 | STEVEN WECHSLER |
Contact Information
| Contractor | Farahi Construction Inc; Lic. No.: 584288-C53 | , |
| Contractor | Farahi Kamran; Lic. No.: 584288-C53 | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/11/2024 | Approved | RYAN SALAZAR |
| Rough-Electrical | 3/11/2024 | Approved | RYAN SALAZAR |
| Rough-Plumbing | 3/11/2024 | Approved | RYAN SALAZAR |
| Deputy Shotcrete | 3/13/2024 | Conditional Approval | JUAN VALENZUELA |
| Grounding or Bonding | 3/20/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Gas Piping or Gas Test | 4/11/2025 | Approved | JAVIER RAMOS JR |
| Enclosure/Fence | 5/8/2025 | Corrections Issued | JAVIER RAMOS JR |
| Pool Equipment Noise Test | 5/15/2025 | Approved | ALFREDO FLORES |
| Enclosure/Fence | 8/11/2025 | Approved | JAVIER RAMOS JR |
| Final | 8/11/2025 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Final | 10/6/2025 | OK to Issue CofO | MISAEL ESPARZA |