17480 W ROSCOE BLVD 91325
Certificate Information: 17480 W ROSCOE BLVD 91325
- Application / Permit
- 24047-20000-00113
- Plan Check / Job No.
- B24VN00975
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 29'-5" x 15'-5" IRREGULAR SHAPED SWIMMING POOL AND 9'-0" IN DIAMETER SPA PER LA CITY STANDARD PLAN #268.
- Permit Issued
- Issued on 8/1/2024
- Issuing Office
- Current Status
- CofO Issued on 9/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 1/25/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 6/6/2024 | SARKIS HARABEDIAN |
| Issued | 8/1/2024 | APPLICANT |
| CofO in Progress | 9/5/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 9/10/2025 | RUBEN SALAS |
| CofO Issued | 9/10/2025 | RUBEN SALAS |
| Permit Finaled | 9/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/6/2024 | ENRIQUE ACOSTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 1/16/2025 | Corrections Issued | MISAEL ESPARZA |
| Grounding or Bonding | 1/16/2025 | Partial Approval | MISAEL ESPARZA |
| Pool Piping | 1/16/2025 | Approved | MISAEL ESPARZA |
| Pre-Gunite | 1/16/2025 | Approved | MISAEL ESPARZA |
| Rough-Electrical | 1/16/2025 | Approved | MISAEL ESPARZA |
| Rough-Plumbing | 1/16/2025 | Approved | MISAEL ESPARZA |
| Gas Piping or Gas Test | 1/23/2025 | Approved | SALVADOR MARTINEZ |
| Deck | 3/19/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Deck | 3/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Deck | 4/1/2025 | Approved | RAUL OLAGI |
| Enclosure/Fence | 5/8/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Enclosure/Fence | 5/9/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Enclosure/Fence | 5/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Enclosure/Fence | 6/2/2025 | Conditional Approval | SALVADOR MARTINEZ |
| Equipment Noise Level | 7/29/2025 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 8/28/2025 | Approved | GAREN HAYRAPETYAN |
| Excavation/Setback/Form/Re-Bar | 8/28/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 8/28/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Order to Comply | 8/28/2025 | Not Required | GAREN HAYRAPETYAN |
| PLUMBING-Final | 8/28/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Final | 9/5/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 9/5/2025 | SGSOV Approved | GAREN HAYRAPETYAN |