876 N NORMAN PL 90049
Certificate Information: 876 N NORMAN PL 90049
- Application / Permit
- 24047-20000-00062
- Plan Check / Job No.
- B24VN00625
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 8' x 8' spa within 30' x 12' pool per standard plan #268 and supplemntal engineered details and design.
- Permit Issued
- Issued on 2/13/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2024 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 1/29/2024 | ARAMIK SHAHMIRZAIAN |
| Building Plans Picked Up | 2/5/2024 | APPLICANT |
| Plan Check Approved | 2/13/2024 | PINANK PATEL |
| Issued | 2/13/2024 | APPLICANT |
| CofO in Progress | 1/31/2025 | CARLOS MATAMOROS |
| CofO in Progress | 1/31/2025 | CARLOS MATAMOROS |
| Permit Finaled | 2/1/2025 | RICHARD STEINBACH |
| CofO Issued | 2/1/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/1/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/24/2024 | ARAMIK SHAHMIRZAIAN |
Contact Information
| Contractor | Coastal Aquatic Creations; Lic. No.: 697943-C53 | 11730 GATEWAY BLVD LOS ANGELES, CA 90064 |
| Engineer | Haddad,, Raymond M; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 6/25/2024 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 8/9/2024 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 8/12/2024 | Approved | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 8/12/2024 | Approved | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 8/12/2024 | Approved | CARLOS MATAMOROS |
| Pool Piping | 8/12/2024 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 8/12/2024 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 8/12/2024 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 8/12/2024 | Approved | CARLOS MATAMOROS |
| Deputy Shotcrete | 8/22/2024 | Conditional Approval | MICHAEL PELHAM |
| Deck | 9/20/2024 | Corrections Issued | CARLOS MATAMOROS |
| Deck | 9/23/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deck | 10/8/2024 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 10/17/2024 | Approved | CARLOS MATAMOROS |
| Pool Equipment Noise Test | 10/22/2024 | Approved | EUSEBIO GUZMAN |
| ELECTRICAL-Final | 1/29/2025 | Approved | CARLOS MATAMOROS |
| Final | 1/29/2025 | OK to Issue CofO | CARLOS MATAMOROS |