6041 N SIMPSON AVE 91606
Certificate Information: 6041 N SIMPSON AVE 91606
- Application / Permit
- 24047-20000-00050
- Plan Check / Job No.
- B24VN00505
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL (E) SWIMMING POOL. REDUCE POOL SIZE TO 24'-0" X 14'-4" POOL AND 11'-0" X 6'-0" SPA WITHIN PER STANDARD PLAN #265 AND ENGINEER DETAIL
- Permit Issued
- Issued on 2/23/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 1/24/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/26/2024 | APPLICANT |
| Applicant returned to address corrections | 2/1/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 2/21/2024 | GIOVANNY CHAVEZ |
| Issued | 2/23/2024 | APPLICANT |
| CofO in Progress | 4/30/2025 | JOSE AVILA |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
| CofO Issued | 5/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Champion Pools Inc; Lic. No.: 1105426-C53 | 13840 PAXTON ST PACOIMA, CA 91331 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 2/29/2024 | Not Ready for Inspection | JOHN HAYES |
| Pre-Gunite | 5/31/2024 | Corrections Issued | JOSE AVILA |
| Pre-Gunite | 6/13/2024 | Corrections Issued | JOSE AVILA |
| Pre-Inspection | 7/5/2024 | Partial Inspection | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 7/22/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 7/23/2024 | Approved | JOSE AVILA |
| Grounding or Bonding | 7/23/2024 | Partial Approval | JOSE AVILA |
| Pre-Gunite | 7/23/2024 | Corrections Issued | JOSE AVILA |
| Pre-Gunite | 7/29/2024 | Approved | JOSE AVILA |
| Deputy Shotcrete | 7/31/2024 | Conditional Approval | ROBERT GOLD |
| Grounding or Bonding | 10/18/2024 | Approved | JOSE AVILA |
| Enclosure/Fence | 11/19/2024 | Corrections Issued | JOSE AVILA |
| Pool Equipment Noise Test | 1/31/2025 | Approved | ALFREDO FLORES |
| Final | 4/30/2025 | OK to Issue CofO | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 4/30/2025 | SGSOV Approved | JOSE AVILA |