13627 W SYLVAN ST 91401

Certificate Information: 13627 W SYLVAN ST 91401

Application / Permit
24047-20000-00042
Plan Check / Job No.
B24VN00391
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW IRR. 16' x 19' SWIMMING POOL WITH 11' X 7' SPA PER CITY STD PLAN 268
Permit Issued
Issued on 1/25/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2024 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 LUISANGEL VALENZUELA
Corrections Issued 1/11/2024 LUISANGEL VALENZUELA
Issued 1/25/2024 APPLICANT
CofO in Progress 6/3/2024 SALVADOR MARTINEZ
CofO Issued 11/15/2024 DANIEL ORRANTE
Permit Finaled 11/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 1/24/2024 WALTER RAMIREZ

Contact Information

Contractor Aqua Pool & Spa Construction Inc; Lic. No.: 1046115-C53 7361 ETHEL AVE #4      NORTH HOLLYWOOD, CA 91605
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 3/19/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Pre-Gunite 3/19/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 3/26/2024 Approved ROBERTO PALACIOS-LOPEZ
Gas Piping or Gas Test 3/26/2024 Approved ROBERTO PALACIOS-LOPEZ
Pool Piping 3/26/2024 Approved ROBERTO PALACIOS-LOPEZ
Pre-Gunite 3/26/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/26/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Deputy Shotcrete 3/28/2024 Conditional Approval JUAN VALENZUELA
Deck 4/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Enclosure/Fence 5/10/2024 Approved RYAN SALAZAR
Equipment Noise Level 5/23/2024 Approved FELIPE PENICHE
Pool Equipment Noise Test 5/23/2024 Approved FELIPE PENICHE
Final 5/24/2024 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/24/2024 SGSOV Approved OGANES TARAKHCHYAN
Final 5/31/2024 OK to Issue CofO SALVADOR MARTINEZ