2452 N JUPITER DR 90046
Certificate Information: 2452 N JUPITER DR 90046
- Application / Permit
- 24047-20000-00041
- Plan Check / Job No.
- B24VN00386
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New Pool (26'x 13') and Internal Spa (10' x 13') on Piles. All work per Engineering.
- Permit Issued
- Issued on 3/5/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 1/21/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 1/24/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 1/25/2024 | APPLICANT |
| Plan Check Approved | 3/5/2024 | VAHAN JIVALAGIAN |
| Issued | 3/5/2024 | APPLICANT |
| CofO in Progress | 9/22/2025 | ROY SPAULDING |
| Permit Finaled | 10/2/2025 | DEROLD HAUFF |
| CofO Issued | 10/2/2025 | DEROLD HAUFF |
| Permit Finaled | 10/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/22/2024 | VAHAN JIVALAGIAN |
Contact Information
| Contractor | Raub Doug Design & Development Inc; Lic. No.: 723625-B | 14066 ROBLAR ROAD SHERMAN OAKS, CA 91423 |
| Engineer | Cristescu,, Barbu Dan; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
| Geologist | Hoek,, Johan; Lic. No.: EG2544 | 10369 SILVERSTON AVE TUJUNGA, CA 91042 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 4/1/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Other (see comments) | 4/2/2024 | Conditional Approval | ROY SPAULDING |
| Deputy Other (see comments) | 4/5/2024 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 4/8/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Other (see comments) | 4/9/2024 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 7/17/2024 | Approved | RAUL BARAJAS |
| Pool Piping | 7/17/2024 | Approved | RAUL BARAJAS |
| Rough-Electrical | 7/17/2024 | Partial Approval | RAUL BARAJAS |
| Rough-Plumbing | 7/17/2024 | Approved | RAUL BARAJAS |
| Deputy Other (see comments) | 7/18/2024 | Conditional Approval | RAUL BARAJAS |
| Gas Piping or Gas Test | 1/28/2025 | Not Ready for Inspection | ROY SPAULDING |
| Grounding or Bonding | 1/28/2025 | Approved | ROY SPAULDING |
| Pool Piping | 1/28/2025 | Approved | ROY SPAULDING |
| Rough-Electrical | 1/28/2025 | Approved | ROY SPAULDING |
| Rough-Plumbing | 1/28/2025 | Approved | ROY SPAULDING |
| Enclosure/Fence | 3/21/2025 | Corrections Issued | ROY SPAULDING |
| Gas Piping or Gas Test | 3/21/2025 | Approved | ROY SPAULDING |
| Pool Piping | 3/21/2025 | Approved | ROY SPAULDING |
| Rough-Electrical | 3/21/2025 | Approved | ROY SPAULDING |
| Rough-Plumbing | 3/21/2025 | Approved | ROY SPAULDING |
| Enclosure/Fence | 3/28/2025 | Approved | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 4/14/2025 | Approved | ROY SPAULDING |
| Final | 4/14/2025 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 4/14/2025 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 4/14/2025 | Approved | ROY SPAULDING |
| Pre-Gunite | 4/14/2025 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Not Ready | ROY SPAULDING |
| Pool Equipment Noise Test | 4/15/2025 | Approved | MIKE WANG |
| Final | 4/21/2025 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 4/21/2025 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Approved | ROY SPAULDING |
| Final | 9/22/2025 | OK to Issue CofO | ROY SPAULDING |