2189 N SUMMITRIDGE DR 90210
Certificate Information: 2189 N SUMMITRIDGE DR 90210
- Application / Permit
- 24047-10000-01822
- Plan Check / Job No.
- B24LA37582
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- EPLAN-NEW 14' X 35' SWIMMING POOL AND BAJA PER ENGINEER DESIGN. "COMPLY WITH DEPARTMENT ORDER effective date 11/16/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
- Permit Issued
- Issued on 4/17/2025
- Issuing Office
- Current Status
- Issued on 4/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2024 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 1/2/2025 | ARAMIK SHAHMIRZAIAN |
| Applicant returned to address corrections | 1/21/2025 | MADISON ODELL |
| Applicant returned to address corrections | 4/3/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 4/8/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 4/17/2025 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 2/10/2025 | MATHEW QUAN |
| Construction near power lines | Cleared | 3/27/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Brite Pool Plastering; Lic. No.: 976733-C53 | , |
| Engineer | Tajvidi,, Seyed Mohammad; Lic. No.: C84559 | 9163 LEROY STREET SAN GABRIEL, CA 91775 |
| Engineer | Tajvidi,, Seyed Mohammad; Lic. No.: NA84559 | , |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/15/2025 | Approved | PETER RUBIO |
| Deputy Shotcrete | 5/23/2025 | Conditional Approval | MARK BEVELAQUA |
| Grounding or Bonding | 9/3/2025 | Approved | PETER RUBIO |
| Enclosure/Fence | 11/19/2025 | Approved | PETER RUBIO |
| Excavation/Setback/Form/Re-Bar | 12/16/2025 | Approved | PETER RUBIO |
| Final | 12/16/2025 | Not Ready for Inspection | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Approved | PETER RUBIO |