120 N GLENROY AVE 90049
Certificate Information: 120 N GLENROY AVE 90049
- Application / Permit
- 24047-10000-01690
- Plan Check / Job No.
- B24LA34169
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- SPA ADDITION AND RELOCATE (E) POOL PER ENGINEERING DESIGN.
- Permit Issued
- Issued on 3/14/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | DANIEL YIP |
| Corrections Issued | 12/10/2024 | DANIEL YIP |
| Quality Review Completed | 12/12/2024 | KEN GILL |
| Building Plans Picked Up | 12/13/2024 | APPLICANT |
| Applicant returned to address corrections | 3/6/2025 | DANIEL YIP |
| Plan Check Approved | 3/14/2025 | DANIEL YIP |
| Issued | 3/14/2025 | APPLICANT |
| CofO in Progress | 10/2/2025 | CARLOS MATAMOROS |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
| CofO Issued | 10/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/6/2025 | DANIEL YIP |
| Tract Map conditions | Cleared | 3/12/2025 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2025 | DIANA RENTERIA |
| Miscellaneous | Cleared | 3/14/2025 | DIANA RENTERIA |
Contact Information
| Contractor | Matt Boyd Contracting; Lic. No.: 824995-B | 11601 WILSHIRE BLVD STE 500 LOS ANGELES, CA 90025 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
| Engineer | Haro,, Ruben; Lic. No.: GE2990 | 899 PIERCE COURT THOUSAND OAKS, CA 91360 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 4/10/2025 | Conditional Approval | CARLOS MATAMOROS |
| Pre-Gunite | 4/10/2025 | Partial Approval | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 4/14/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Other (see comments) | 4/17/2025 | Conditional Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 4/21/2025 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 5/9/2025 | Approved | KIRK SANDERS |
| Grounding or Bonding | 6/5/2025 | Approved | CARLOS MATAMOROS |
| Pool Piping | 6/5/2025 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 6/25/2025 | Corrections Issued | BOBBY KEY |
| Gas Piping or Gas Test | 7/9/2025 | Partial Approval | SEAN HAUPT |
| Deck | 7/22/2025 | Approved | MEL KHACHATOURIAN |
| Enclosure/Fence | 8/21/2025 | Approved | CARLOS MATAMOROS |
| Final | 9/24/2025 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 9/26/2025 | Corrections Issued | CARLOS MATAMOROS |
| Final | 9/26/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 9/26/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/1/2025 | Approved | CARLOS MATAMOROS |
| Final | 10/1/2025 | OK to Issue CofO | CARLOS MATAMOROS |