13158 W OTSEGO ST 91423

Certificate Information: 13158 W OTSEGO ST 91423

Application / Permit
24047-10000-01687
Plan Check / Job No.
B24LA34063
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ePlan. NEW SWIMMING POOL WITH SPA PER LADBS STANDARD PLAN #268.
Permit Issued
Issued on 2/12/2025
Issuing Office
Current Status
CofO Issued on 1/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2024 APPLICANT
Assigned to Plan Check Engineer 12/2/2024 DANIEL SANJUAN
Corrections Issued 12/3/2024 DANIEL SANJUAN
Applicant returned to address corrections 12/19/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 12/24/2024 ROSENDO MEDINA
Applicant returned to address corrections 1/1/2025 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 1/4/2025 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 1/16/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 2/11/2025 ROSENDO MEDINA
Issued 2/12/2025 APPLICANT
CofO in Progress 12/11/2025 OGANES TARAKHCHYAN
Permit Finaled 1/7/2026 RUBEN SALAS
CofO Issued 1/7/2026 RUBEN SALAS
Permit Finaled 1/7/2026 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 12/17/2024 WALTER RAMIREZ

Contact Information

Contractor Agam Pool And Spa Inc; Lic. No.: 993464-C53       ,
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 2/25/2025 Approved OGANES TARAKHCHYAN
Deputy Shotcrete 2/26/2025 Conditional Approval ROBERT GOLD
Grounding or Bonding 4/10/2025 Approved OGANES TARAKHCHYAN
Enclosure/Fence 5/29/2025 Approved OGANES TARAKHCHYAN
Equipment Noise Level 7/9/2025 Approved FELIPE PENICHE
Excavation/Setback/Form/Re-Bar 10/3/2025 Approved RYAN SALAZAR
Final 10/3/2025 Corrections Issued RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 10/3/2025 SGSOV Approved RYAN SALAZAR
Final 11/24/2025 Corrections Issued OGANES TARAKHCHYAN
Final 12/11/2025 OK to Issue CofO OGANES TARAKHCHYAN