10508 W DUNLEER DR 90064
Certificate Information: 10508 W DUNLEER DR 90064
- Application / Permit
- 24047-10000-01686
- Plan Check / Job No.
- B24LA34038
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan. NEW POOL AND SPA PER CITY STANDARD PLAN WITH SOIL REPORT AND ENGINEER DETAIL
- Permit Issued
- Issued on 4/2/2025
- Issuing Office
- Current Status
- CofO Issued on 6/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | KHUONG TRUONG |
| Corrections Issued | 12/26/2024 | KHUONG TRUONG |
| Quality Review Completed | 12/27/2024 | GARO TELMI |
| Applicant returned to address corrections | 3/27/2025 | KHUONG TRUONG |
| Plan Check Approved | 4/2/2025 | KHUONG TRUONG |
| Issued | 4/2/2025 | APPLICANT |
| CofO in Progress | 6/12/2026 | BOBBY KEY |
| Permit Finaled | 6/13/2026 | RICHARD STEINBACH |
| CofO Issued | 6/13/2026 | RICHARD STEINBACH |
| Permit Finaled | 6/13/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/26/2024 | KHUONG TRUONG |
| Specific Plan | Cleared | 3/21/2025 | JAZMIN ROQUE |
| ZA Case | Cleared | 3/21/2025 | JAZMIN ROQUE |
| Construction near power lines | Cleared | 4/1/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ganeshwara,, Vela; Lic. No.: GE2736 | 19420 KILFINAN ST PORTER RANCH, CA 91326 |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/29/2025 | Approved | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 6/24/2025 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 6/24/2025 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 6/24/2025 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 6/24/2025 | Approved | ARAM AVEDISIAN |
| Deputy Shotcrete | 7/21/2025 | Conditional Approval | MICHAEL PELHAM |
| Grounding or Bonding | 11/13/2025 | Approved | MICHAEL ALLEN |
| Enclosure/Fence | 1/21/2026 | Corrections Issued | ASHLEY THOMPSON |
| Enclosure/Fence | 1/27/2026 | Approved | MICHAEL ALLEN |
| Equipment Noise Level | 2/24/2026 | Approved | JUAN ESCOTO DELGADO |
| Final | 3/3/2026 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 3/3/2026 | SGSOV Approved | ASHLEY THOMPSON |
| Final | 6/1/2026 | OK to Issue CofO | ASHLEY THOMPSON |