2215 S GLYNDON AVE 90291
Certificate Information: 2215 S GLYNDON AVE 90291
- Application / Permit
- 24047-10000-01659
- Plan Check / Job No.
- B24LA33248
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New Swimming Pool with spa included per LA standard plan #268 with modified detail
- Permit Issued
- Issued on 1/31/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 11/26/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 1/31/2025 | SHANGQIN XIE |
| Issued | 1/31/2025 | APPLICANT |
| Permit Finaled | 10/10/2025 | RICHARD STEINBACH |
| CofO Issued | 10/10/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/10/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Artistry Pools; Lic. No.: 1097346-C53 | 2671 MACEO ST LOS ANGELES, CA 90065 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/10/2025 | Partial Approval | JESUS RODRIGUEZ |
| Deck | 4/8/2025 | Approved | JAYLIN GRAVITTE |
| Enclosure/Fence | 5/21/2025 | Approved | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 7/3/2025 | Approved | BOBBY KEY |
| Final | 7/3/2025 | Corrections Issued | BOBBY KEY |
| Green Building Final | 7/3/2025 | Approved | BOBBY KEY |
| Green Building Rough | 7/3/2025 | Approved | BOBBY KEY |
| Pre-Gunite | 7/3/2025 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/3/2025 | SGSOV Not Ready | BOBBY KEY |
| Pool Equipment Noise Test | 7/17/2025 | Approved | JAMES VORHIS |
| ELECTRICAL-Final | 10/7/2025 | Approved | JESUS RODRIGUEZ |
| Final | 10/7/2025 | Partial Approval | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/7/2025 | SGSOV Approved | JESUS RODRIGUEZ |