1742 S PREUSS ROAD 90035

Certificate Information: 1742 S PREUSS ROAD 90035

Application / Permit
24047-10000-01650
Plan Check / Job No.
B24LA33012
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA PER STD PLAN 270
Permit Issued
Issued on 2/7/2025
Issuing Office
Metro
Current Status
CofO Issued on 1/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2024 APPLICANT
Assigned to Plan Check Engineer 11/21/2024 NGHI SU
Corrections Issued 11/21/2024 NGHI SU
Plan Check Approved 2/7/2025 AUNG SOE
Issued 2/7/2025 APPLICANT
CofO in Progress 1/21/2026 WILBER ROSALES
Permit Finaled 1/29/2026 RICHARD STEINBACH
CofO Issued 1/29/2026 RICHARD STEINBACH
Permit Finaled 1/29/2026 RICHARD STEINBACH

Permit Application Clearance Information

Construction near power lines Cleared 12/14/2024 RIDWAN HARDY

Contact Information

Architect Rezvani,, Farbod; Lic. No.: C32315 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Contractor Di Nalli Consulting Llc; Lic. No.: 942979-B 9055 ALCOTT STREET UNIT 1      LOS ANGELES, CA 90035
Engineer Cristescu,, Barbu Dan; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/26/2025 Corrections Issued EVAN COOPER
Pre-Gunite 2/26/2025 Approved KENNETH NAGLE
Pre-Gunite 2/26/2025 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Not Ready EVAN COOPER
Deputy Shotcrete 2/27/2025 Conditional Approval MICHAEL PELHAM
Pre-Inspection 2/27/2025 Corrections Issued EVAN COOPER
Gas Piping or Gas Test 8/21/2025 Approved JAYLIN GRAVITTE
Grounding or Bonding 8/21/2025 Approved JAYLIN GRAVITTE
Enclosure/Fence 10/30/2025 Approved EVAN COOPER
Pool Equipment Noise Test 12/16/2025 Approved JUAN ESCOTO DELGADO
Excavation/Setback/Form/Re-Bar 1/8/2026 Approved WILBER ROSALES
Final 1/8/2026 Conditional Approval WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 1/8/2026 SGSOV Approved WILBER ROSALES
Final 1/20/2026 OK to Issue CofO WILBER ROSALES