122 S FORMOSA AVE 90036
Certificate Information: 122 S FORMOSA AVE 90036
- Application / Permit
- 24047-10000-01533
- Plan Check / Job No.
- B24LA30507
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL & SPA ( 20.5 ft x 16 ft and 6 ft depth) , # 268.
- Permit Issued
- Issued on 2/18/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 11/5/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 2/4/2025 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 2/12/2025 | DANIEL SMILEY |
| Plan Check Approved | 2/18/2025 | TSE MING HUANG |
| Issued | 2/18/2025 | APPLICANT |
| CofO in Progress | 6/10/2025 | JOSE MACIAS |
| No Progress | 6/14/2025 | DEROLD HAUFF |
| CofO in Progress | 6/14/2025 | DEROLD HAUFF |
| Permit Finaled | 7/3/2025 | DEROLD HAUFF |
| CofO Issued | 7/3/2025 | DEROLD HAUFF |
| Permit Finaled | 7/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 11/21/2024 | JORGE RUIZ |
| Specific Plan | Cleared | 11/21/2024 | JORGE RUIZ |
| Specific Plan | Cleared | 11/21/2024 | JORGE RUIZ |
| Construction near power lines | Cleared | 1/25/2025 | RIDWAN HARDY |
| CPC | Cleared | 2/12/2025 | DAVID URITA |
| CPC | Cleared | 2/12/2025 | DAVID URITA |
Contact Information
| Contractor | Poolworks Design Inc; Lic. No.: 597631-C53 | 9510 VISTA ALETA VALLEY CENTER, CA 92082 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/26/2025 | Approved | JOSE MACIAS |
| Gas Piping or Gas Test | 3/11/2025 | Approved | JOSE MACIAS |
| Grounding or Bonding | 3/11/2025 | Approved | JOSE MACIAS |
| Pool Piping | 3/11/2025 | Approved | JOSE MACIAS |
| Pre-Gunite | 3/11/2025 | Approved | JOSE MACIAS |
| Rough-Electrical | 3/11/2025 | Approved | JOSE MACIAS |
| Rough-Plumbing | 3/11/2025 | Approved | JOSE MACIAS |
| Deputy Shotcrete | 3/25/2025 | Conditional Approval | JOSE MACIAS |
| Enclosure/Fence | 5/7/2025 | Approved | JOSE MACIAS |
| Pool Equipment Noise Test | 5/16/2025 | Approved | ANDEY CHAPARRO |
| Final | 5/19/2025 | Corrections Issued | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Approved | JOSE MACIAS |
| Final | 6/9/2025 | OK to Issue CofO | JOSE MACIAS |