4949 N SANCOLA AVE 91601
Certificate Information: 4949 N SANCOLA AVE 91601
- Application / Permit
- 24047-10000-01521
- Plan Check / Job No.
- B24LA30020
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Remodel pool and spa and relocate pool equipment per LA standard plan.
- Permit Issued
- Issued on 11/15/2024
- Issuing Office
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2024 | DANIEL SMILEY |
| Plan Check Approved | 11/1/2024 | DANIEL SMILEY |
| Issued | 11/15/2024 | APPLICANT |
| CofO in Progress | 6/30/2025 | JOSE AVILA |
| CofO Issued | 9/25/2025 | RUBEN SALAS |
| Permit Finaled | 9/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Piping or Gas Test | 1/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Rough-Electrical | 1/21/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Rough-Plumbing | 1/21/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 1/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Gas Piping or Gas Test | 1/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Grounding or Bonding | 1/28/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Pool Piping | 1/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Pre-Gunite | 1/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Rough-Electrical | 1/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Rough-Plumbing | 1/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Deputy Shotcrete | 1/30/2025 | Conditional Approval | JUAN VALENZUELA |
| Gunite | 2/5/2025 | Partial Inspection | JOSE AVILA |
| Grounding or Bonding | 3/21/2025 | Approved | JOSE AVILA |
| Enclosure/Fence | 5/7/2025 | Corrections Issued | JOSE AVILA |
| Enclosure/Fence | 5/12/2025 | Not Ready for Inspection | JOSE AVILA |
| Enclosure/Fence | 5/13/2025 | Corrections Issued | JOSE AVILA |
| Enclosure/Fence | 5/16/2025 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Final | 6/5/2025 | Approved | JOSE AVILA |
| Equipment Noise Level | 6/5/2025 | Approved | FELIPE PENICHE |
| PLUMBING-Final | 6/5/2025 | Approved | JOSE AVILA |
| Final | 6/20/2025 | Corrections Issued | JOSE AVILA |
| Final | 6/30/2025 | OK to Issue CofO | JOSE AVILA |