1243 N COMMONWEALTH AVE 90029

Certificate Information: 1243 N COMMONWEALTH AVE 90029

Application / Permit
24047-10000-01436
Plan Check / Job No.
B24LA27648
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
Eplan - New 26'x7' pool and 8'x7' spa
Permit Issued
Issued on 2/13/2025
Issuing Office
Current Status
CofO Issued on 12/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2024 APPLICANT
Assigned to Plan Check Engineer 10/23/2024 ALEXANDER JOO
Corrections Issued 10/24/2024 ALEXANDER JOO
Applicant returned to address corrections 11/14/2024 TSE MING HUANG
Applicant returned to address corrections 11/14/2024 ALEXANDER JOO
Applicant returned to address corrections 12/30/2024 CARLOS MONTES
Plan Check Approved 1/16/2025 ALEXANDER JOO
Issued 2/13/2025 APPLICANT
CofO in Progress 11/7/2025 FREDDIE RIVERA
No Progress 11/10/2025 DEROLD HAUFF
CofO in Progress 11/10/2025 DEROLD HAUFF
Permit Finaled 12/13/2025 DEROLD HAUFF
CofO Issued 12/13/2025 DEROLD HAUFF
Permit Finaled 12/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/30/2024 ALEXANDER JOO

Contact Information

Contractor Owner-Builder       ,
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/13/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Gas Piping or Gas Test 3/13/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Gunite 3/13/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Gas Piping or Gas Test 3/20/2025 Partial Inspection FREDDIE RIVERA
Gunite 3/20/2025 Approved FREDDIE RIVERA
Pre-Gunite 3/20/2025 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/20/2025 SGSOV Not Ready FREDDIE RIVERA
Gas Piping or Gas Test 3/27/2025 Partial Inspection FREDDIE RIVERA
Pre-Gunite 3/27/2025 Corrections Issued FREDDIE RIVERA
Rough-Electrical 3/27/2025 Partial Inspection FREDDIE RIVERA
Rough-Plumbing 3/27/2025 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Not Ready FREDDIE RIVERA
Gas Piping or Gas Test 4/1/2025 Approved FREDDIE RIVERA
Grounding or Bonding 4/1/2025 Approved FREDDIE RIVERA
Rough-Electrical 4/1/2025 Approved FREDDIE RIVERA
Rough-Plumbing 4/1/2025 Corrections Issued FREDDIE RIVERA
Deputy Shotcrete 4/3/2025 Conditional Approval FREDDIE RIVERA
Deck 7/17/2025 Approved FREDDIE RIVERA
Enclosure/Fence 10/15/2025 Corrections Issued FREDDIE RIVERA
Enclosure/Fence 10/17/2025 No Access for Inspection FREDDIE RIVERA
Enclosure/Fence 10/20/2025 Approved FREDDIE RIVERA
ELECTRICAL-Final 11/3/2025 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 11/3/2025 Approved FREDDIE RIVERA
Final 11/3/2025 Partial Inspection FREDDIE RIVERA
Pre-Gunite 11/3/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/3/2025 SGSOV Approved FREDDIE RIVERA
Final 11/6/2025 OK to Issue CofO FREDDIE RIVERA
Pool Equipment Noise Test 11/6/2025 Approved ROBERT CHAVEZ
ELECTRICAL-Final 11/25/2025 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 11/25/2025 Partial Inspection FREDDIE RIVERA