3635 S MOORE ST 90066

Certificate Information: 3635 S MOORE ST 90066

Application / Permit
24047-10000-01287
Plan Check / Job No.
B24LA23593
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
Eplan: New Swimming Pool and Spa per Standard Plan #268
Permit Issued
Issued on 3/6/2025
Issuing Office
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/22/2024 APPLICANT
Assigned to Plan Check Engineer 9/25/2024 DAVID CASTILLO
Corrections Issued 9/26/2024 DAVID CASTILLO
Applicant returned to address corrections 10/22/2024 DAVID CASTILLO
Applicant returned to address corrections 11/25/2024 JOHNPAUL ISIP
Applicant returned to address corrections 12/4/2024 ALFREDO JARA
Plan Check Approved 12/12/2024 JOHNPAUL ISIP
Issued 3/6/2025 APPLICANT
CofO in Progress 3/18/2026 DAKOTA LOW
Permit Finaled 3/26/2026 RICHARD STEINBACH
CofO Issued 3/26/2026 RICHARD STEINBACH
Permit Finaled 3/26/2026 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/9/2024 VASIL MIHALEV
Construction near power lines Cleared 11/22/2024 RIDWAN HARDY
Construction within easement Cleared 11/22/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/8/2025 Partial Approval MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 5/20/2025 Approved MICHAEL ALLEN
Green Building Rough 5/20/2025 Approved MICHAEL ALLEN
Pool Piping 5/20/2025 Approved MICHAEL ALLEN
Pre-Gunite 5/20/2025 Approved MICHAEL ALLEN
Rough-Plumbing 6/12/2025 Approved MICHAEL ALLEN
Deck 6/27/2025 Approved JAYLIN GRAVITTE
Enclosure/Fence 7/15/2025 Approved MICHAEL ALLEN
Equipment Noise Level 10/28/2025 Approved EUSEBIO GUZMAN
ELECTRICAL-Final 10/31/2025 Approved WILBER ROSALES
Final 10/31/2025 Corrections Issued WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Approved WILBER ROSALES
Final 2/13/2026 Corrections Issued RUBEN RIVAS
Green Building Final 2/13/2026 Approved RUBEN RIVAS
Final 3/13/2026 Partial Approval DAKOTA LOW
Final 3/18/2026 OK to Issue CofO DAKOTA LOW