3604 N HAYVENHURST AVE 91436

Certificate Information: 3604 N HAYVENHURST AVE 91436

Application / Permit
24047-10000-01148
Plan Check / Job No.
B24LA19239
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
*** Eplan *** New engineered pool 23'-2" X 11'-0" at rear of SFD, replacing existing freeshaped pool. 1 of 2
Permit Issued
Issued on 11/7/2024
Issuing Office
Current Status
CofO in Progress on 2/17/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/21/2024 APPLICANT
Assigned to Plan Check Engineer 9/5/2024 CHUNG-WEN CHUANG
Corrections Issued 9/23/2024 CHUNG-WEN CHUANG
Applicant returned to address corrections 10/29/2024 CHUNG-WEN CHUANG
Plan Check Approved 10/30/2024 CHUNG-WEN CHUANG
Issued 11/7/2024 APPLICANT
CofO in Progress 2/17/2026 SEAN WIRCH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/26/2024 ROBERT PINA
Specific Plan Cleared 10/17/2024 ALEX VELA

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVENUE      VAN NUYS, CA 91406
Geologist Van, Meter, James L.; Lic. No.: EG2031 6634 VALJEAN AVE      VAN NUYS, CA 91406
Landscape Architect Segal,, Joshua Eric; Lic. No.: LA5815 500 CORNELL DR      BURBANK, CA 91504

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/9/2025 Corrections Issued THOMAS FINNILA
Pre-Gunite 1/9/2025 Not Ready for Inspection THOMAS FINNILA
Rough-Electrical 1/9/2025 Approved THOMAS FINNILA
Rough-Plumbing 1/9/2025 Approved THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 1/22/2025 Conditional Approval THOMAS FINNILA
Pre-Gunite 1/22/2025 Conditional Approval THOMAS FINNILA
Rough-Electrical 1/22/2025 Partial Approval THOMAS FINNILA
Rough-Plumbing 1/22/2025 Approved THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 1/28/2025 Approved JOHN COLEMAN
Pre-Gunite 1/28/2025 Approved JOHN COLEMAN
Rough-Electrical 1/28/2025 Approved JOHN COLEMAN
Rough-Plumbing 1/28/2025 Approved JOHN COLEMAN
Deputy Shotcrete 2/3/2025 Partial Approval SEAN WIRCH
Deck 3/4/2025 Corrections Issued JOHN COLEMAN
Deck 3/18/2025 Approved JOHN COLEMAN
Enclosure/Fence 7/29/2025 No Access for Inspection MORRIS JACKSON
Enclosure/Fence 8/1/2025 Corrections Issued THOMAS FINNILA
Enclosure/Fence 8/29/2025 Corrections Issued THOMAS FINNILA
Enclosure/Fence 9/5/2025 Corrections Issued THOMAS FINNILA
Enclosure/Fence 10/29/2025 Corrections Issued THOMAS FINNILA
Enclosure/Fence 11/17/2025 Approved THOMAS FINNILA
Equipment Noise Level 1/26/2026 Approved ALFREDO FLORES
ELECTRICAL-Final 2/13/2026 Approved SEAN WIRCH
Final 2/13/2026 OK to Issue CofO SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Approved SEAN WIRCH