17055 W RANCHO ST 91316
Certificate Information: 17055 W RANCHO ST 91316
- Application / Permit
- 24047-10000-00833
- Plan Check / Job No.
- B24LA11555
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- EPLAN (N) SWIMMING POOL AND SPA, 42'x16'. MAX DEPTH: 5 FT. POOL PER STANDARD PLAN#268 AND SOILS REPORT.
- Permit Issued
- Issued on 10/9/2024
- Issuing Office
- Current Status
- CofO in Progress on 9/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2024 | ADRIANA LOPEZ |
| Corrections Issued | 7/15/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 8/6/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 9/10/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 10/9/2024 | ADRIANA LOPEZ |
| Issued | 10/9/2024 | APPLICANT |
| CofO in Progress | 9/6/2025 | MICHAEL PELHAM |
| No Progress | 9/6/2025 | MICHAEL PELHAM |
| CofO in Progress | 9/6/2025 | MICHAEL PELHAM |
| CofO in Progress | 9/29/2025 | MORRIS JACKSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2024 | BIAINA HARITUNIAN |
| Watercourse | Cleared | 8/5/2024 | BIAINA HARITUNIAN |
| Excavation more than 5-ft deep | Cleared | 9/10/2024 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 9/10/2024 | ADRIANA LOPEZ |
Contact Information
| Contractor | Flexi - Tech Contracting Inc; Lic. No.: 767683-C53 | , |
| Engineer | Lin,, Chi Hsin; Lic. No.: GE2921 | 123 N VALENCIA ST ALHAMBRA, CA 91801 |
| Geologist | Kruger,, Mark Otto; Lic. No.: EG2345 | 10120 NATIONAL BLVD LOS ANGELES, CA 90034 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 10/18/2024 | Partial Approval | JON MCHUGH |
| Pre-Gunite | 10/18/2024 | Approved | JON MCHUGH |
| Special/Order Compliance | 10/18/2024 | Corrections Issued | JON MCHUGH |
| Deputy Shotcrete | 10/23/2024 | Conditional Approval | JON MCHUGH |
| Gas Piping or Gas Test | 3/3/2025 | Approved | MORRIS JACKSON |
| Rough-Electrical | 3/3/2025 | Partial Inspection | MORRIS JACKSON |
| Deck | 3/7/2025 | Approved | JON MCHUGH |
| Enclosure/Fence | 4/23/2025 | Approved | JON MCHUGH |
| Equipment Noise Level | 5/20/2025 | Approved | ALFREDO FLORES |
| Pool Equipment Noise Test | 5/20/2025 | Approved | ALFREDO FLORES |
| ELECTRICAL-Final | 9/4/2025 | Approved | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 9/4/2025 | Approved | SEAN WIRCH |
| Final | 9/4/2025 | Partial Approval | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Approved | SEAN WIRCH |
| Final | 9/29/2025 | Corrections Issued | MORRIS JACKSON |