4205 N AGNES AVE 91604
Certificate Information: 4205 N AGNES AVE 91604
- Application / Permit
- 24047-10000-00769
- Plan Check / Job No.
- B24LA10807
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL WITH SPA PER LA CITY STANDARD PLAN #268 AND ENGINEER DETAIL 551-70
- Permit Issued
- Issued on 10/3/2024
- Issuing Office
- Current Status
- CofO Issued on 8/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2024 | MADISON ODELL |
| Corrections Issued | 6/7/2024 | MADISON ODELL |
| Applicant returned to address corrections | 7/27/2024 | MADISON ODELL |
| Applicant returned to address corrections | 9/12/2024 | MADISON ODELL |
| Applicant returned to address corrections | 9/24/2024 | SERGIO MUNIZ |
| Plan Check Approved | 10/2/2024 | SERGIO MUNIZ |
| Issued | 10/3/2024 | APPLICANT |
| CofO in Progress | 7/10/2025 | JAVIER RAMOS JR |
| Permit Finaled | 8/27/2025 | RUBEN SALAS |
| CofO Issued | 8/27/2025 | RUBEN SALAS |
| Permit Finaled | 8/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/7/2024 | TINA MIRANDA |
Contact Information
| Architect | Biglin,, Brian W; Lic. No.: C29771 | 1152 ADIRONDACK COURT SIMI VALLEY, CA 93065 |
| Contractor | Advanced Construction; Lic. No.: 801955-B | , |
| Contractor | Gemilyan Karen; Lic. No.: 801955-B | , |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
| Geologist | Barrett,, Mark A; Lic. No.: EG2088 | 14428 HAMLIN ST 200 VAN NUYS, CA 91401 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/25/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Special/Order Compliance | 10/25/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 11/1/2024 | Approved | CHRISTOPHER ROJAS |
| Pre-Gunite | 11/7/2024 | Approved | CHRISTOPHER ROJAS |
| Rough-Electrical | 11/7/2024 | Approved | CHRISTOPHER ROJAS |
| Rough-Plumbing | 11/7/2024 | Approved | CHRISTOPHER ROJAS |
| Grounding or Bonding | 3/19/2025 | Approved | CHRISTOPHER ROJAS |
| Equipment Noise Level | 6/16/2025 | Approved | FELIPE PENICHE |
| Final | 6/16/2025 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 6/16/2025 | SGSOV Not Required | JAVIER RAMOS JR |
| Final | 7/10/2025 | OK to Issue CofO | JAVIER RAMOS JR |