9618 W ARROWOOD DR 90210

Certificate Information: 9618 W ARROWOOD DR 90210

Application / Permit
24047-10000-00755
Plan Check / Job No.
B24LA10516
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ePlan. New 12'x25' infinity edge swimming pool and 6'x6' spa with three steps and a pool cover per std plan 268. 1 OF 2
Permit Issued
Issued on 10/1/2024
Issuing Office
Current Status
CofO Issued on 3/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 MICHAEL LOPEZ
Corrections Issued 6/14/2024 MICHAEL LOPEZ
Quality Review Completed 6/18/2024 MICHAEL PEREZ
Applicant returned to address corrections 8/7/2024 MICHAEL LOPEZ
Plan Check Approved 9/12/2024 MICHAEL LOPEZ
Issued 10/1/2024 APPLICANT
CofO in Progress 2/27/2025 RAUL BARAJAS
Permit Finaled 3/2/2025 DEROLD HAUFF
Permit Finaled 3/2/2025 DEROLD HAUFF
CofO Issued 3/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/12/2024 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Eckert,, Eddie John; Lic. No.: C34587 630 TRAYER AVE      GLENDORA, CA 91741
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grounding or Bonding 11/1/2024 Approved RAUL BARAJAS
Pool Piping 11/1/2024 Not Ready for Inspection RAUL BARAJAS
Pre-Gunite 11/1/2024 Corrections Issued RAUL BARAJAS
Rough-Plumbing 11/1/2024 Approved RAUL BARAJAS
Pre-Gunite 11/6/2024 Approved RAUL BARAJAS
Deputy Shotcrete 11/18/2024 Conditional Approval BRIAN SULLIVAN
Grounding or Bonding 12/5/2024 Approved RAUL BARAJAS
Gas Piping or Gas Test 12/18/2024 Not Ready for Inspection RAUL BARAJAS
Rough-Electrical 12/18/2024 Approved RAUL BARAJAS
Enclosure/Fence 1/7/2025 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 1/15/2025 Not Ready for Inspection RAUL BARAJAS
Enclosure/Fence 1/15/2025 Corrections Issued RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/15/2025 Approved RAUL BARAJAS
Final 1/15/2025 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 1/15/2025 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV Not Ready RAUL BARAJAS
Enclosure/Fence 1/22/2025 Approved RAUL BARAJAS
Pool/Spa Cover 1/31/2025 Approved RAUL BARAJAS
Final 2/24/2025 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 2/24/2025 SGSOV Not Ready RAUL BARAJAS
Final 2/26/2025 OK to Issue CofO RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Approved RAUL BARAJAS