12227 W TWEED LANE 90049
Certificate Information: 12227 W TWEED LANE 90049
- Application / Permit
- 24047-10000-00724
- Plan Check / Job No.
- B24LA09914
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL AND SPA AT REAR OF LOT. 35'x14', 6ft max depth. PER STANDARD PLAN #254.
- Permit Issued
- Issued on 8/6/2024
- Issuing Office
- Current Status
- CofO in Progress on 9/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2024 | ADRIANA LOPEZ |
| Corrections Issued | 6/2/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 6/7/2024 | KEN GILL |
| Building Plans Picked Up | 6/11/2024 | APPLICANT |
| Applicant returned to address corrections | 7/25/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 8/6/2024 | ADRIANA LOPEZ |
| Issued | 8/6/2024 | APPLICANT |
| CofO in Progress | 9/25/2025 | HERBERT GIRON |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 7/25/2024 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 7/25/2024 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lin,, Chi Hsin; Lic. No.: GE2921 | 123 N VALENCIA ST ALHAMBRA, CA 91801 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Shotcrete | 8/12/2024 | No Access for Inspection | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 8/19/2024 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 8/19/2024 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 8/19/2024 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 8/19/2024 | Approved | ARAM AVEDISIAN |
| Deputy Shotcrete | 8/22/2024 | Conditional Approval | ARAM AVEDISIAN |
| Grounding or Bonding | 3/11/2025 | Approved | HERBERT GIRON |
| Enclosure/Fence | 5/14/2025 | Corrections Issued | HERBERT GIRON |
| Enclosure/Fence | 5/21/2025 | Not Ready for Inspection | HERBERT GIRON |
| Enclosure/Fence | 5/23/2025 | Conditional Approval | ARAM AVEDISIAN |
| Equipment Noise Level | 5/27/2025 | Not Ready for Inspection | JAMES VORHIS |
| Equipment Noise Level | 5/29/2025 | Approved | JAMES VORHIS |
| Final | 6/2/2025 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/2/2025 | SGSOV Approved | HERBERT GIRON |
| Final | 7/29/2025 | Not Ready for Inspection | HERBERT GIRON |
| Final | 8/7/2025 | Corrections Issued | HERBERT GIRON |
| Final | 9/24/2025 | Not Ready for Inspection | HERBERT GIRON |
| Final | 9/25/2025 | OK to Issue CofO | HERBERT GIRON |