2307 S LOUELLA AVE 90291
Certificate Information: 2307 S LOUELLA AVE 90291
- Application / Permit
- 24047-10000-00683
- Plan Check / Job No.
- B24LA09246
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan (N) 20' X 12' POOL WITH 7'-6" X 12' SPA PER STD PLAN #268
- Permit Issued
- Issued on 6/13/2024
- Issuing Office
- Current Status
- CofO Issued on 5/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2024 | ISIS ARGUETA |
| Corrections Issued | 5/30/2024 | ISIS ARGUETA |
| Plan Check Approved | 6/12/2024 | ISIS ARGUETA |
| Issued | 6/13/2024 | APPLICANT |
| Permit Finaled | 5/27/2025 | RICHARD STEINBACH |
| CofO Issued | 5/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/11/2024 | Approved | DAVID FEILER |
| Gas Piping or Gas Test | 10/11/2024 | Corrections Issued | DAVID FEILER |
| Pre-Gunite | 10/11/2024 | Approved | DAVID FEILER |
| Rough-Electrical | 10/11/2024 | Approved | DAVID FEILER |
| Rough-Plumbing | 10/11/2024 | Approved | DAVID FEILER |
| Deck | 1/14/2025 | Approved | JAYLIN GRAVITTE |
| Grounding or Bonding | 1/14/2025 | Approved | JAYLIN GRAVITTE |
| Special/Order Compliance | 1/14/2025 | Partial Inspection | BOBBY KEY |
| Enclosure/Fence | 3/11/2025 | Approved | JESUS RODRIGUEZ |
| Pool Equipment Noise Test | 3/20/2025 | Not Ready for Inspection | EUSEBIO GUZMAN |
| Pool Equipment Noise Test | 3/25/2025 | Approved | EUSEBIO GUZMAN |
| ELECTRICAL-Final | 4/9/2025 | Approved | JESUS RODRIGUEZ |
| Final | 4/9/2025 | Partial Approval | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/9/2025 | SGSOV Approved | JESUS RODRIGUEZ |