233 S ROCKINGHAM AVE 90049

Certificate Information: 233 S ROCKINGHAM AVE 90049

Application / Permit
24047-10000-00591
Plan Check / Job No.
B24LA07997
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ePlan. New Pool ontop existing structure Plan checker to create seperate grading permit MISSING ALL GRADING DETIALS, NOT PROVIDED
Permit Issued
Issued on 6/28/2024
Issuing Office
Current Status
CofO Issued on 6/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2024 APPLICANT
Assigned to Plan Check Engineer 5/2/2024 MARCELA FRANQUEZ
Corrections Issued 5/4/2024 MARCELA FRANQUEZ
Quality Review Completed 5/17/2024 GARO TELMI
Plan Check Approved 6/26/2024 MARCELA FRANQUEZ
Issued 6/28/2024 APPLICANT
CofO in Progress 6/3/2026 HERBERT GIRON
Permit Finaled 6/11/2026 RICHARD STEINBACH
CofO Issued 6/11/2026 RICHARD STEINBACH
Permit Finaled 6/11/2026 RICHARD STEINBACH

Permit Application Clearance Information

ZA Case Cleared 6/6/2024 DANIEL CORONADO
Grading Pre-Inspection Cleared 6/26/2024 MARCELA FRANQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Shniderman,, Jason Bernard; Lic. No.: C20524 16000 SHERMAN WAY #234      VAN NUYS, CA 91607

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Shotcrete 8/2/2024 Conditional Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 8/5/2024 Corrections Issued KENNETH NAGLE
Grounding or Bonding 8/7/2024 Partial Approval ARAM AVEDISIAN
Pool Piping 8/7/2024 Partial Approval ARAM AVEDISIAN
Pre-Gunite 8/7/2024 Partial Approval ARAM AVEDISIAN
Deputy Shotcrete 8/12/2024 Conditional Approval ARAM AVEDISIAN
Rough-Plumbing 8/23/2024 Not Ready for Inspection JESUS RODRIGUEZ
Rough-Plumbing 9/19/2024 Approved JESUS RODRIGUEZ
Deputy Drilled-In Anchors 10/31/2024 Conditional Approval JESUS RODRIGUEZ
Pre-Inspection 9/24/2025 Partial Inspection HERBERT GIRON
Gas Piping or Gas Test 9/26/2025 Not Ready for Inspection HERBERT GIRON
Gas Piping or Gas Test 10/1/2025 Not Ready for Inspection HERBERT GIRON
Grounding or Bonding 10/2/2025 Approved HERBERT GIRON
Gas Piping or Gas Test 10/6/2025 Approved HERBERT GIRON
Grounding or Bonding 2/9/2026 Approved HERBERT GIRON
Enclosure/Fence 2/12/2026 Partial Inspection HERBERT GIRON
Enclosure/Fence 4/21/2026 Approved HERBERT GIRON
Excavation/Setback/Form/Re-Bar 4/21/2026 Approved HERBERT GIRON
Pre-Gunite 4/21/2026 Approved HERBERT GIRON
Final 5/29/2026 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Approved HERBERT GIRON
Equipment Noise Level 6/2/2026 Approved BRIAN CHRISTIAN
Final 6/3/2026 OK to Issue CofO HERBERT GIRON