941 N STONEHILL LANE 90049

Certificate Information: 941 N STONEHILL LANE 90049

Application / Permit
24047-10000-00532
Plan Check / Job No.
B23LA19368
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL
Permit Issued
Issued on 1/27/2025
Issuing Office
Current Status
Issued on 1/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/31/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 CARLOS MONTES
Corrections Issued 11/15/2023 CARLOS MONTES
Quality Review Completed 11/16/2023 GARO TELMI
Applicant returned to address corrections 4/18/2024 CARLOS MONTES
Applicant returned to address corrections 8/6/2024 CARLOS MONTES
Applicant returned to address corrections 12/12/2024 CARLOS MONTES
Plan Check Approved 1/27/2025 CARLOS MONTES
Issued 1/27/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/13/2024 ROBERT PINA

Contact Information

Architect Lind,, Eric Christopher; Lic. No.: NA16909       ,
Contractor Owner-Builder       ,
Engineer Garcia,, Ramon; Lic. No.: NA4595       ,
Engineer Shniderman,, Jason Bernard; Lic. No.: C20524 16000 SHERMAN WAY #234      VAN NUYS, CA 91607
Engineer Vardeh,, Edmond; Lic. No.: C56992 43 INVERARY      TRABUCO CANYON, CA 92679
Geologist Hogrefe,, Scott Joseph; Lic. No.: EG1516 3157 ESCOLLERA AVE      SANTA ROSA VALLEY, CA 93012

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 3/21/2025 Partial Approval KEVIN SARGSYAN
Deputy Other (see comments) 4/1/2025 Conditional Approval MICHAEL PELHAM
Pre-Inspection 4/17/2025 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 4/18/2025 Corrections Issued KEVIN SARGSYAN
Deputy Drilled-In Anchors 4/21/2025 Conditional Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 4/21/2025 Partial Approval KEVIN SARGSYAN
Deputy Drilled-In Anchors 5/7/2025 Conditional Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 5/12/2025 Partial Approval KEVIN SARGSYAN
Deputy Other (see comments) 5/13/2025 Conditional Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 5/30/2025 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 6/2/2025 Partial Approval KEVIN SARGSYAN
Pre-Gunite 6/12/2025 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 6/16/2025 Partial Approval KEVIN SARGSYAN
Deputy Other (see comments) 6/17/2025 Conditional Approval KEVIN SARGSYAN
Deputy Drilled-In Anchors 7/8/2025 Conditional Approval KEVIN SARGSYAN
Deputy Other (see comments) 7/24/2025 Conditional Approval KEVIN SARGSYAN
Deputy Other (see comments) 7/31/2025 Conditional Approval KEVIN SARGSYAN
Pre-Gunite 8/18/2025 Not Ready for Inspection STEPHANIE SWANSON
Pre-Gunite 8/21/2025 Corrections Issued KEVIN SARGSYAN
Pre-Gunite 8/27/2025 Conditional Approval KEVIN SARGSYAN
Deputy Drilled-In Anchors 8/29/2025 Conditional Approval KEVIN SARGSYAN
Deputy Shotcrete 9/8/2025 Conditional Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 9/10/2025 Partial Approval KEVIN SARGSYAN
Gas Piping or Gas Test 1/26/2026 Approved KEVIN SARGSYAN
Enclosure/Fence 2/4/2026 Not Ready for Inspection KEVIN SARGSYAN
Rough-Plumbing 2/4/2026 Not Ready for Inspection KEVIN SARGSYAN
Enclosure/Fence 2/5/2026 Corrections Issued KEVIN SARGSYAN
Enclosure/Fence 2/20/2026 Not Ready for Inspection KEVIN SARGSYAN
Enclosure/Fence 2/24/2026 Not Ready for Inspection KEVIN SARGSYAN